Industrial Buildings
A safer and better working environment
for industrial buildings
The advantage for study found a number of
drivers for change; cost, sustainability; fire resistance and security.
Any alternative to steel portal frames would
have to not only be of comparative cost but also offer better programme
times and be an architecturally attractive option for designers and
structurally have the ability to be easily used with non-concrete
components. In addition, the structural solution should have widely
available components and resources from competitive specialists.
Taking all of the above into consideration,
the best alternative solution to steel portal frames is a concrete
load-bearing wall with a lightweight roof. This is a very
straightforward design and construction approach that can be easily
adapted. The load-bearing walls can be either propped or
cantilevered. For the propped wall, the stability comes initially from
push-pull props. When the roof is complete the props are removed as the
roof then provides the propping force and takes the horizontal loads
back to the flank walls. For the cantilevered option, the walls
cantilever from the base and do not need any propping or reliance on
the on the roof for stability. However, these walls do need to be
thicker than propped walls.
Both wall options offer the same range of
benefits that are of particular value for this market:
- They are structurally multi-functional in
that they carry the vertical load and provide all the longitudinal
bracing
- They provide, without additional cost,
thermal efficiency, fire resistance and security
- They do not have intrusive columns that
can account for up to 5% of space in portal frame sheds
- They can be used with many types of roof
structures
- They can be produced off-site or on-site
with all the chosen finishes fixed in place prior to erection thus
improving quality, site safety and construction speed
- They offer high levels of air-tightness,
notoriously difficult with steel portal frames due to the multitude of
metal joints
- When cast on site using locally-produced
ready-mix concrete they reduce the CO2 emissions associated with
transportation
- They use reinforcing steel which is made
from 100% recycled material.
STEEL OR CONCRETE?
The increased steel price there has already brought a noticeable
increase in the use of concrete columns in warehouses.
The cost of concrete columns is about half the cost of steel columns.
Many consultants still design warehouses in the traditional way,
in steel, mainly because that is what they are familiar with.
CLIENTS’ WAREHOUSE REQUIREMENTS
The requirements of warehousing for clients has become more
specific i.e. security, fire resistance, insulation, appearance and
durability(in coastal conditions).
The clients that we are targeting are the likes of Nestle, Clicks and
Hirsch group.
PRECAST
In order to effectively compete for market share against steel, it is
necessary to consider precast concrete elements, formed and
constructed on site and on the ground.
Concrete would have the advantage over steel in that the concrete
elements (walls, columns, beams, trusses and slabs) can be constructed
in situ on site or precast on the ground and lifted into their final
position on site, as opposed to steel that has to be prefabricated in a
workshop then transported to site and erected into position.
When forming a precast concrete element on the ground, the ground slab
forms the majority of the formwork. The vertical formwork height would
be the thickness of the section of the element. Consider a concrete
column 20 m high constructed in situ as opposed to forming and
constructing it on the ground and the lifting it into position with a
crane.
Concrete can compete favourably against steel with all elements in
warehouses, except the roof sheeting (unless security is a critical
issue)
The foundations for concrete will be heavier
than for a normal portal frame solution. However, the loading on the
ground will be a line load from the walls rather than point loads from
columns. This would simplify the foundations. For cantilever walls the
foundations will most likely have to be piled as would the propped wall
option if the ground capacity is low or the shed walls are high.
The cladding can be whatever is required. A
major benefit of using concrete walls is that if a masonry or concrete
finish is required then this could be incorporated into the manufacture
of the inner skin. Both skins can be lifted into position in one
operation thereby saving construction time.
The construction of the roof is also
simplified with concrete walls as, unlike with steel portal frames, the
roof beams are simply supported on the walls. The spacing of the roof
beams could be optimised as they would not be reliant on the portal
frame spacing. Roofs may be light or heavyweight. A heavyweight roof
would provide extra thermal insulation and mass.
With all their benefits, it is surprising
that the use of concrete walls for industrial sheds is not widespread
in South Africa as it is throughout Continental Europe. One of the main
reasons for this may simply be inertia. The continued rise in steel
prices and the development of a viable concrete option will do much to
address this. The Cement & Concrete Institute plans to work with
the concrete industry partners such as Tilt up Charles Van Eck, the
concrete contractors group, and product manufacturers to facilitate the
availability of a real alternative to the tin shed.
|