|
Concrete cricket pitches
Introduction
Although most clubs can maintain turf pitches of sufficiently
high standard to meet their annual fixture lists, few are able to provide
turf areas of a standard which will permit proper practice and coaching.
All too often the so-called practice pitch is so bumpy that any attempt
at stroke play is futile, and the unpredictable behaviour of a ball bowled
down such a pitch constitutes a positive danger to seasoned and inexperienced
players alike.
Concrete provides a permanent solution to the problem of ever-increasing
maintenance costs associated with the traditional turf pitch, whether
for matches or for practice. It is
now possible to simulate, very closely, the characteristics of a natural
surface and at the same time provide a number of additional benefits:
a concrete pitch base, with a synthetic playing surface to cater for spin
and to prevent excessive wear of the cricket balls, is virtually maintenance
free, it does not suffer form the effects of drought, it is extremely
difficult to vandalize and it cannot be damaged by being played on when
wet.
In fact, a concrete-based match strip, set in the middle of the ground,
avoids the need for a separate practice pitch and also provides an opportunity
for full-scale practice including fielding and wicket-keeping.
Typical pitch layouts
Figure 1: Alternative layouts for match pitches

Figure 2: Layout for practice
pitch

Figure 1 shows two alternatives that
can be considered for match pitches; the choice will depend on individual
requirements.
Figure 1(a) shows the ideal situation where both run-ups and pitch are
constructed to a width of 2,75 m which is a little wider than the width
between the return creases. With this arrangement play can take place
much sooner than usual after rain, as bowlers will be able to obtain a
firm foothold. Figure 1(b) shows a pitch of minimum length and width.
In both match and practice pitches the stumps should not be fixed directly
in the concrete but in an opening in the concrete measuring 300 x 150
mm formed at a suitable position and later filled with clay.
Site preparation
Generally, the tasks involved in preparing
a site for a concrete-based pitch are the same for each type of base.
Mark out the plan area of the pitch and excavate to a depth of 100 mm
plus the thickness of the surfacing mat. Any soft spongy spots should
be further excavated and filled with dry, hard material. Check the depth
of the excavation by bridging across with a scratch template (Figure 3)
then compact the excavation either by rolling or by tamping. Check the
compacted surface of the excavation from ground level in the same way
as the depth of the excavation.
Figure 3: Trimming the excavation
using a scratch template

Fix side forms
around the perimeter of the intended slab to contain the concrete until
it has hardened. The forms should be 95 mm deep, of either metal or timber
95 mm x 32 mm planed hardwood is suitable held securely
in place by steel spikes or wooden stakes. 3 mm hardboard pieces should
be used as shims between the ground and the
bottom edges of the side forms to bring the forms to the correct height.
The level along the pitch should follow the lie of the ground; gauge it
with a taut string stretched between
pegs at each end of the pitch. Check the level across the pitch with a
spirit level, allowing a slight crossfall of about 12 mm to one side.
Before placing concrete, paint the inner faces of the formwork with a
thin film of release agent clean lubricating oil is suitable.
The concrete
Concrete can be obtained in various ways, depending on the quantity required.
Buying cement and aggregate separately and mixing them on site in a hired
or borrowed concrete mixer is probably the cheapest method of obtaining
concrete, but demands a lot of effort. You will also need storage space
for the materials. Cement must be kept as dry as possible; if it cannot
be stored indoors it should be stacked on a raised timber
platform and completely covered with waterproof sheeting.
For mixing on site, use the proportions given in Table 1, based on a bag
of cement. The approximate quantities of material required can be calculated
from Tables 2 and 3.
The amount of water used in the mix should be only enough to make the
mix easily workable. If the mix is too dry it will be difficult to compact
and if it is too wet it will not attain the desired strength.
The mixing must be thorough, and the mixed concrete should be of uniform
colour and texture before it is placed.
Table 1: Mix proportions for site mixing per bag of cement
* Other cements may be used in consultation with the
manufacturer.
Table 2: Materials per m3 of concrete

Table 3: Approximate concrete
quantities (Quantities are net; increase quantities by about 10% when
ordering to allow for wastage.)

Ready-mixed concrete is far more economical
in terms of time and effort but can present problems of access to the
site. It should be remembered that the concrete is delivered in very heavy
trucks which can cause a great deal of damage to unprotected grass areas.
If, therefore, full advantage is to be taken of this system and
one of the
main features of ready-mixed concrete is that it can be placed directly
from the mixer truck into a prepared area special precautions must
be taken to protect the route to
the pitch.
Ready-mixed concrete should be specified according to Table 4. Approximate
concrete quantities are given in Table 3.
Table 4: Specification details for ready-mixed concrete

Reinforcement
The reinforcement required is a Ref-245 cross-welded steel wire mesh and
it should be placed 40 to 50 mm from the surface. The reinforcement must
not cross the central
transverse joint but should terminate 50 mm from the joint and the side
forms. Any overlaps required should be a minimum of 300 mm.
Placing the reinforcement is described under Placing and compacting the
concrete.
Central joint
The central joint indicated in Layouts 1(a) and 1(b) may be formed in
one of two ways.
- Grooved Joint (see Figure 4) This is used
when the whole pitch is to be placed in one operation. To make a grooved
joint, a steel blade about 3 mm wide is forced down into the fresh concrete
to a depth of 25 mm. It is then withdrawn leaving a groove into which
is dropped a strip of either bituminous roofing felt (eg Malthoid) or
hardboard 3 mm thick cut to size. Surface finishing of the concrete
can then be completed.
Figure 4: Grooved joint.

- Keyed Joint (see Figure 5) This is used
when half of the pitch is placed on one day and the other half on a
subsequent day. It is formed by nailing a 20 mm halfround to the timber
form at middepth of the concrete. After the form is removed the face
of the concrete should be painted with limewash prior to the adjacent
concrete being placed.
Figure 5: Keyed joint

Placing and compacting the concrete
The compacted ground under the concrete must be damped ahead of concreting
to prevent water being drawn out of the fresh concrete. However, any free
surface water should be removed before the concrete is placed.
The concrete should be placed and compacted in two stages as follows:
- The concrete is first compacted and screeded off
to a depth of 45 mm below the top edges of the side forms. A notched
screed board as shown in Figure 6 should be used. The concrete is initially
placed and roughly levelled off slightly higher than the required level
(a notched template may be used for this). The notched screed board
is then used with a chopping action to compact the concrete. When the
concrete is compacted the notched screed board is used with a sawing
action, while sliding on the side forms, to screed the concrete to the
required level.
Immediately this has been done, the reinforcement
is placed on the concrete, with overlaps as necessary.*
- As soon as the reinforcement is in position the
rest of the concrete is placed and compacted and levelled off using
a straight screed board so that the finished concrete is level with
the top edges of the forms.
Surface finishing
The ideal surface is a fine matt texture that will be suitable for applying
a synthetic playing surface or, if the concrete is left uncovered, will
not be slippery when wet. Trowelling with steel trowels is used to achieve
such a surface but it must not be started until:
- Bleeding of the mix has ceased.
- All bleed water on the surface has evaporated
or been removed.
- The surface has started to stiffen.
A considerable downward force should
be exerted on the trowel during the finishing operation. Trowelling should
continue until the surface has attained an even, fine matt finish.
Small amounts of water, flicked on with a brush, may be applied
to the surface to aid finishing, but as this tends to weaken the surface
it should be done as little as possible and only where trowelling alone
is not producing the desired results.
Note: Planning of the work should take into account that the delay
period before steel trowelling can start is likely to be 2 to 3 hours,
and longer in cold weather.
During the delay period, drying of the mix, as opposed to evaporation
of bleed water, must be avoided as it may lead to cracking.
- Laying reinforcing fabric on the ground before
concrete is placed and lifting it into position while placing, or placing
it on the finished surface of the concrete and pushing it in should
not be permitted, as these methods give no assurance that the reinforcement
will end up in a true plane at the required depth below the surface.
Figure 6: Notched screed board

Curing
It is essential, if the concrete is to develop the desired strength, that
it be kept damp for an adequate period after casting. Damp-curing should
be continued for at least 10 days in warm weather and 14 days in cold
weather. The curing procedure recommended is to cover the work, as soon
as surface texturing is complete, with plastic sheeting that is kept in
place with a thin, uniform layer of sand or soil over it and stones along
the edges. To avoid damage to the surface which may occur when plastic
sheeting is laid direct on wet concrete, the sheeting may be supported
clear of the surface by timber battens for the first 24 hours of curing.
Wind must not be allowed to blow under the sheeting.
Applying the synthetic playing surface
If such a surface is to be applied, the manufacturers instructions
should be followed carefully. They may include the requirement that the
concrete be allowed to dry out first.
Cement &
Concrete Institute
PO Box 168, Halfway House, 1685
Tel (011) 315-0300 Fax (011) 315-0584 e-mail info@cnci.org.za website
http://www.cnci.org.za
Published by the Cement & Concrete Institute, Midrand, 1997, reprinted
1999, 2001.
©Cement & Concrete Institute
|