BUILDING A PIZZA OVEN
1. Introduction
Building a pizza oven for entertaining family and friends
makes a satisfying and challenging DIY project. This leaflet
gives guidance on the selection of materials as well as
providing step-by-step instructions on how to construct a
pizza oven for home use. This oven is not intended for the
constant use required for a commercial enterprise.
The material quantities given are for an oven of the
dimensions listed below. While 'scaled down' versions
are possible, sufficient space is required for the fire and to
enable the pizzas to be turned during cooking. This size has
proved to be effective.
2. Materials
The pizza oven described here is constructed of burnt clay
bricks with cement mortared joints.
Throughout this leaflet, 'cement' means a common cement
complying with SANS 50197-1/SABS ENV 197-1, strength
class 32,5 or higher and carrying the SABS mark.
2.1 Bricks
Use well burnt solid clay bricks. Dimensions, especially
thickness, should be as uniform as possible. Although it is
not necessary to use face bricks, they are more uniform and
look more attractive, especially if the dome is not plastered.
Cement bricks are not recommended for the dome since
they do not withstand heat as well as clay bricks. Use of
refractory (fire) bricks is not necessary and will only add to
the cost.
Always pre-soak burnt clay bricks before building with them.
2.2 Mortar
A mortar of fine sand, preferably a building sand, and
cement is suitable.
Use a common cement complying with SANS 50197-1/
SABS ENV 197-1, strength class 32,5 or higher and carrying
the SABS mark.
It is not necessary to use high-alumina cement which is
expensive and not readily available from retail outlets.
The mortar must not be too strong: use 5 buckets of loose
damp sand to 1 bucket of cement and enough water to
make a plastic mixture.
3. Dimensions
Foundation slab diameter .............. 1,8 m
Suspended slab diameter .............. 1,6 m
Dome inside diameter .................... 1,2 m approx
Dome outside diameter .................. 1,4 m approx
Door opening, width ....................... 440mm approx
Door opening height ....................... 260mm approx
4. Quantities of material used
4.1 Base slab
2 x 50 kg bags of cement
3 wheelbarrows of concrete sand
2 wheelbarrows of 13,2 or 19mm concrete stone
(13,2mm stone produces a concrete that is easier
to place)
4.2 Base
150 clay bricks (222 x 106 x 73mm)
Mortar
1 x 50 kg bag of cement
2 wheelbarrows of building sand
4.3 Suspended slab
1,5 x 50 kg bags of cement
1,5 wheelbarrows concrete sand
1,25 wheelbarrows of 13,2 or 19mm concrete stone
(13,2mm stone produces a concrete that is easier
to place)
30 m of 6 or 8mm diameter steel reinforcing rod
Support for concrete slab - strong board is required as
formwork on which to cast the slab. Suitable boards
are 19mm shutter board or shutter ply.
5 m x 75mm strips of 4 to 6mm plywood, masonite or
other suitable flexible material for the side forms to
support the fresh concrete.
16 x 1,8 m precast concrete lintels (only if used as an
alternative to casting the suspended slab)
Note: These quantities were for a 1,6 m outside
diameter round base with a 106mm wall.
4.4 Dome, chimney and oven floor
200 clay bricks (222 x 106 x 73mm) for the dome
and chimney
2 wheelbarrows of building sand
1 bag of cement
35 litres of small (5 to 10mm) crushed stone for the
insulation layer under the paving bricks
1,5 m² of clay paving bricks
9 m² of 4mm masonite or plywood to be used as
temporary dome support
5. Tools
Spade and pick
Tape measure
Spirit Level
Trowel (brick laying)
Angle grinder (230mm)
Masonry cutting disks (5 x 230mm)
Wheelbarrow
Wood float
Jigsaw for cutting board to support the dome
Marking pen for marking bricks and boards for cutting
Rubber gloves. Work with mortar is very 'hands on' and
gloves protect from hand damage
Pointing tool (to finish mortar between bricks after laying)
Broomstick, pick handle, 38 x 38mm length of timber
or similar, to compact concrete
Straight edge - any flat-edged plank, piece of steel
tubing etc can be used
Black plastic sheet for curing
6. Construction
6.1 Base Slab
Mark out a 1,8 m diameter circle on the ground. This
can be achieved by using two nails and string. Tie one
nail to the end of the string and tie the other nail so
that it is 900mm away from the first nail. It is best to
use a piece of string that does not stretch easily.
Secure one of the nails in the centre and use the other
nail to scribe a circle around it.
Excavate the area within the circle to a depth of
75mm. Use a spirit level to ensure that the surface
is level. Compact the area well and wet the ground
before placing concrete.
Cast a 75mm thick slab in the excavation using
medium strength concrete.
Base slab approximate material requirements:
- 2 x 50 kg bags of cement
- 3 Wheelbarrows of concrete sand
- 2 Wheelbarrows of 13,2 or 19mm concrete stone
(13,2mm stone produces a concrete that is easier
to place)
Use a tin or bucket of convenient size for batching all the
solid ingredients.
The following mix proportions should be used:
Compact the concrete well by tamping it all over using
a broomstick, pick handle, a length of 38 x 38mm
timber or similar object. Finish the surface off using
a straight edge and spirit level to ensure the top
surface is level and flat. After the surface has been
levelled, leave the concrete to stand for a while until
the surface water evaporates and the concrete stiffens
slightly. Use a wood float to finish the surface.
The concrete can now be covered with a plastic sheet
to prevent moisture loss and ensure effective curing.
Keep the slab covered for 7 days.
6.2 Brickwork for base
Mark the centre of the foundation slab. Draw a 1,6 m
diameter circle on the foundation slab using two nails
tied 800mm apart on a piece of string. This is the
outside diameter of the base wall.
Mark out the position and width (500 - 600mm) of the
opening in the base. The opening is used to access the
storage space under the pizza oven.
Proportions and quantities of materials:
150 Clay bricks (222 x 106 x 73mm)
Mortar
1 x 50 kg bag of cement
2 Wheelbarrows of building sand
Water - add in small quantities, mixing after each addition, until the mix is soft and plastic.
Mix a small batch of bedding mortar at a time. If too
much mortar is mixed it will begin to stiffen before it
can be used and will need to be thrown away.
Do not add water to mortar that has stiffened to
retemper it as this will weaken it.
Note: this allows for some wastage.
Use a tin or bucket of convenient size for batching all the
solid ingredients.
The following mix proportions should be used:
- The base is built up to a convenient working height.
Nine courses of bricks are recommended.
It is very time consuming to lay bricks using a spirit
level to line them up. An alternative method is to
set up a perpendicular pole/pipe/broomstick or similar
in the centre of the slab and use some form of pointer
that rotates around it to indicate the position and
height of the bricks.
For example, a 20mm round tube can be used as
the perpendicular guide and a short piece of 25mm
tube slipped over it with a pointer fastened to it.
The pointer can be a piece of mild steel rod
680 x 6mm welded perpendicular to this short piece
of tubing. The pointer is positioned so that its tip is
85mm above the foundation slab. Marks are
then made on the perpendicular guide tube every
85mm above this reference mark. A 'G' clamp can
be clamped onto the perpendicular guide tube at each
marking to hold the pointing device at the correct level.
As brickwork progresses, this pointer is rotated to
indicate the height and position of each brick. Although
this takes time to set up, it makes accurate brick laying
much quicker. (See photograph right.)
Unless the base will be plastered, a pointing tool
is now used to finish the mortar between the bricks. To
improve bond strength and make brick laying easier,
clay bricks should be pre-soaked. If 'cement bricks'
are used for the base, they should be laid dry.
To allow the mortar to continue to gain strength, it is
recommended that the brickwork be kept wet for
7 days after completion of the brickwork.
6.3 Suspended slab
The suspended slab can be cast in situ or made using
precast concrete lintels. If concrete lintels are used, they
need to be carefully chosen. Find a supplier of straight
lintels that have been carefully and neatly cast. The lintels
will need to be positioned on the base and cut to fit.
A cast-in-situ slab requires careful preparation, but the
end result can be neat and satisfying. Temporary support
and formwork is required to hold the concrete until it gains
sufficient strength to be self supporting. This support must
be strong enough to hold the entire weight of fresh concrete
and the loads imposed during placing and finishing.
- Strong board is required as formwork, on which to cast
the slab. The board must not distort during or after
concrete placing. Suitable boards include 19mm
shutter board or shutter ply.
The board is placed over the top of the brickwork and
the inside shape of the base marked on the board
from underneath. The board is then removed and cut
to shape so that it fits inside the brickwork of the base.
In order to be able to remove the board after the
concrete has gained strength, it is advisable to cut it
down the centre so that the two halves can be
removed from the base opening later.
Make sure the board is well supported under the join
during casting of the fresh concrete. The joint in the
board and the joint between the board and brickwork
must be sealed to prevent paste loss from the fresh
concrete. There are various options available including
joint sealer, foam strips squeezed into the gaps, thin
plastic sheeting over the join, duct tape, etc. Another
option is to cover the entire surface with a plastic sheet.
- Sturdy support will be required under the board to hold
it up in position during concrete placing and curing.
A simple method is to use brick 'pillars' in several
places under the board. These pillars can be
constructed by stacking bricks in a pillar formation
without the use of bedding mortar. At least seven
support pillars will be required to support the
formwork board, six around the circumference and
one in the middle. After curing the slab for 7 days,
the pillars can be taken out easily by wiggling out a
few loose bricks, allowing the pillar to collapse.
DO NOT remove these pillars too soon, or the
suspended slab could collapse.
- Additional formwork is required around the edges of
the slab. Tie a ratchet strap or sturdy piece of
rope around the top of the base brickwork.
Use the shutter board off cuts to make approximately
15 battens 50mm wide and 200mm long.
Tuck these battens between the strap and the
brickwork around the top of the base.
Allow them to protrude approximately 75mm above
the brickwork. Cut 75mm wide strips from the
4mm to 6mm thick plywood/masonite.
A total length of approximately 5 m will be required.
Cut these strips in the longest possible lengths to
reduce the joins required. This will make it easier to
form a nice round form. Fasten these strips to the
inside of the battens using small screws. Joins in the
strips should coincide with a batten position.
The formwork is now in place to support the fresh
concrete required for the suspended slab.
- To make removal of the formwork easier, a thin layer
of release agent should be applied to the inside of the
side forms as well as the top surface of the base
timber. Spray and Cook, Vaseline or cooking oil have
been found to be satisfactory.
6.4 Casting the suspended slab
For the suspended slab, 0,15 m³ of high-strength concrete
and 30 m of 6 or 8mm diameter steel reinforcing rod will
be required.
Concrete made using relatively small stone is preferable
for casting thin slabs. Although it is possible to use
19mm stone, a maximum stone size of 13,2mm is
recommended.
Concrete proportions and quantities:
The concrete proportions and quantities for the suspended
slab are as follows:
1,5 x 50 kg bags of cement
1,5 Wheelbarrows concrete sand
1,25 Wheelbarrows of 13,2 or 19mm concrete
stone (13,2mm stone produces a concrete that is
easier to place)
Use a tin or bucket of convenient size for batching all the
solid ingredients.
The following mix proportions should be used:
- Concrete is placed in two operations. A 25mm layer of
concrete is placed and compacted on the formwork,
the reinforcing rods are placed in two layers, at right
angles to each other and 150mm apart on top of this
layer. The remaining concrete is immediately placed
and compacted. The delay between placing and
compacting the first layer of concrete and placing
the second layer must be as short as possible.
When compacting the second layer, tamping must be
deep enough to reach the first layer in order for the
concrete to be well bonded. Compact the concrete
very well around the edges to remove excess air.
In conjunction with tamping the concrete, the side
forms can be lightly tapped to help expel excess air.
- Once the concrete has been placed, use a straight
edge in a tamping and sawing motion to produce a
flat surface and to bring sufficient paste to produce
a good finish to the surface. A spirit level is used to
ensure the surface is level in all directions.
- Allow the surface to stiffen slightly and excess water
to evaporate before using a wood float to finish the
surface. For best results allow the surface to further
stiffen before floating a second time.
Adding additional water to the concrete during floating
will weaken the surface.
- Cover the concrete with a plastic sheet to prevent
evaporation and allow it to cure. The plastic should be
well secured all around the edges to prevent wind from
blowing between the plastic and the concrete. For best
results keep the plastic in place until construction of
the oven floor begins. (Allow the suspended slab to
cure for 7 days before removing supports and starting
construction of the dome)
7. Oven Floor
- Mark a 1,4 m circle on the concrete slab to indicate
the position of the oven base. (The nails and string can
again be used, spaced 700mm apart.)
- Identify the location of the oven door and build up
the brickwork to form the opening as seen in the
photograph. Remember to make the door opening
wide and high enough to easily work through and
move pizzas in and out (approximately 440mm wide
x 310mm high, before paving). The bricks across the
top of the door opening require support during
construction. The support is left in for approximately a
week to allow the mortar to gain strength.
- Lay a course of soldier bricks (bricks built up on end) to
form the base of the dome. Use the 1,4 m circle as a
guide to mark the position of the outside surface of this
course of bricks. Allow the mortar to set and gain
strength for at least 24 hours before any further
work is done.
- Spread out a 20 - 25mm layer of 5 to 7mm stone
over the oven floor to provide some insulation for the
oven floor. The volume of blinding stone required is
approximately 35 litres. The top surface of this layer is
carefully levelled to provide a flat surface for laying
the clay paving bricks. The stone layer is tapered
to be thinner near the door to limit restricting the door
opening when laying the paving bricks. Those in the
doorway should be laid in bedding mortar to keep
them in position.
- Lay clay paving bricks over the stone layer to form the
oven floor. The bricks are laid in contact with each
other. No grout is required between them. An angle
grinder is very useful to cut the bricks around the
edges to shape. A hammer and cold chisel can be
used to cut these bricks, but it takes a great deal
of patience to produce a neat job.
8. Dome
8.1 Dome temporary support
The temporary dome support needs to be constructed with
something rigid and strong enough to hold the weight of the
dome but not too strong to be broken out after construction.
Materials such as 4mm plywood or masonite are suitable.
- Mark two lines on the board perpendicular to each
other. The base line length is half the dome floor
diameter minus 15mm (dome floor diameter divided by
2 - 15mm) The dome floor diameter is the diameter
of the inside of the soldier course of bricks. The
perpendicular line length is equal to the proposed
inside height of the dome, (approx. 550mm).
- Use loose bricks laid on the masonite or plywood to
simulate the dome arch shape between two ends of
the lines. Remember to allow for the course of soldier
bricks already in place. Move the bricks around until
a pleasing shape with approximately equal spaces
between the bricks is achieved.
- When an acceptable shape is achieved mark the inside
curve onto the board.
- Cut out the shape that has been developed with a
jigsaw and use it as a template to mark another
24 identical shapes.
- Cover the oven floor with a sheet of plastic to protect
it from mortar that will drop during the dome
construction. Stack the shapes that have been cut
for dome support onto the oven floor in the pattern of
the spokes in a bicycle wheel. The boards will touch
and support each other in the centre of the oven floor.
The boards must be evenly spaced around the
circumference of the floor.
- Construction of the dome can now begin.
8.2 Dome construction
- It is difficult to construct a nice looking dome with full
length bricks. Begin by cutting approximately 50 bricks
into 2/3 and 1/3 and approximately 50 into halves.
More bricks can be cut into desired sizes as
construction of the dome progresses.
Proportions and quantities of materials
200 clay bricks (222 x 106 x 73mm) for the dome and
chimney
2 wheelbarrows of building sand
1 bag of cement
Use a tin or bucket of convenient size for batching all the
solid ingredients.
The following mix proportions should be used:
- Mix a small batch of bedding mortar. Construction of
the dome is a reasonably slow process, and if too
much mortar is mixed it will begin to stiffen before it
can be used and will need to be thrown away.
Do not add water to mortar that has stiffened to
retemper it as this will weaken it.
- Starting with 2/3 - length bricks, begin building the
dome.The inside joint widths need to be kept as small
as possible. When 'buttering' the brick with mortar,
taper the mortar to be thin on the inside but thick
on the outside. Use enough mortar to allow some
to squeeze out when the brick is laid to ensure proper
bedding.
Lay the bricks so that they lie as closely as possible to
the temporary support. Ensure any adjustments made
to brick positioning are made quickly, before the mortar
begins to stiffen. If the mortar has already stiffened,
it's better to remove the brick and apply fresh mortar
before re-positioning.
Ensure that all the joints are well filled with mortar.
Immersing the clay bricks in water just prior to use
improves the mortar bond and gives more time to
adjust the brick position before the mortar stiffens.
- Once the second course of bricks is started, different
length bricks are used to ensure that perpendicular
joints do not fall directly above each other. The bottom
courses are built predominantly with 2/3 - sized bricks.
The middle courses are built mainly with 1/2 bricks and
the top courses with 1/3 - sized bricks.
- The top few courses will require bricks to be cut into
triangular shapes to fit. It may be better to cut these
bricks as they are required.
- An opening for flue gases must be left in the dome.
It's best to make this opening to one side so that heat
does not easily escape out of the top of the oven. An
ideal place for this opening is directly behind and
above the oven door. An opening approximately
400mm wide and 250mm deep is recommended.
- The dome construction is very time consuming.
The final oven appearance is directly proportional to
the degree of patience and care taken during this
stage.
- Once the mortar has set, regularly spray the dome to
prevent the mortar from drying out too quickly. This will
allow it to continue gaining strength. Keep the dome
wet for at least a week.
9. Chimney
- Leave the temporary dome support in place during
construction of the chimney.
- The chimney is constructed so that flue gases remain
in contact with the top of the oven as long as possible
to help retain heat and improve oven efficiency.
- The chimney is constructed by building up above
the oven door and over the top of the oven dome.
Two low parallel 'walls' form the sides of the chimney.
The side walls extend over the top of the dome.
As the side walls are built higher, successive courses
are staggered so that the chimney narrows towards
the top. A spirit level and tape measure are used to
continually check levels and dimensions to produce
a good looking chimney. The final course of bricks
is laid across the top to close off the chimney.
An opening is left at the back end of the chimney
channel to allow flue gases to escape. A low chimney
stack can be built up around this opening.
10. Finishing off and other notes
- Allow at least a week after the dome has been
constructed and at least 24 hours after construction
of the chimney before breaking out the temporary
dome supports.
- A cold chisel can be used to carefully remove excess
mortar that has squeezed out on the inside of the
dome.
- Use a hard bristle brush on the inside of the dome and
on the oven floor to remove any loose particles of grit,
to prevent them from ending up in the first pizzas.
- The oven should be given 2 weeks to allow the mortar
to cure and for excess moisture to evaporate before
being used.
- The outside of the oven can be left as it is, tiled,
plastered or coated with a fire proof layer of insulation.
It is important to remember that the oven will expand
as it heats up and cracks will develop in the dome.
These cracks will probably extend into any dome
covering and will not affect the efficiency of the oven.
- It's important to remember that the heat for cooking
does not only come directly from the fire but also from
heat that has been absorbed by the floor and dome
of the oven. It is especially important to allow the
oven floor to heat up so that the pizzas are also
cooked underneath. For this reason it is necessary to
light the fire several hours before the oven is used.
11. Tips
- Use soft wood that burns quickly and produces a lot of
heat rather than hard, slow burning wood.
- When the oven is hot enough it is difficult to keep your
hand in the entrance.
- If the pizza remains 'soft' underneath when the topping
is cooked the floor is not hot enough. (The pizza falls
apart into a cheesy mess as you try to turn or
remove it, causing subsequent pizzas to stick.) Allow
the oven to heat properly before cooking, and allow
some time between cooking pizzas for the floor to
re heat or alternate pizza cooking positions.
Paddle for turning pizzas
A paddle can be made using 6mm plywood and a sturdy
garden rake handle. A broom handle would work but it is
nice to have the extra length and thickness of a rake handle.
The 6mm plywood was cut to shape ensuring that it was
big enough to hold a pizza but not too big to comfortably fit
through the door.
A 6mm slot was cut in the end of the rake handle and wood
glue used to fasten the plywood 'paddle' in place. The flat
end of the paddle was tapered to about 1mm to ease
'scooping' of pizzas.
Cement & Concrete Institute
PO Box 168, Halfway House, 1685
Tel (011) 315-0300 Fax (011) 315-0584 e-mail info@cnci.org.za website
http://www.cnci.org.za
Published by the Cement & Concrete Institute, Midrand, 2005
©Cement & Concrete Institute
|