Sand-cement screeds and concrete toppings for floors
1.
Introduction
Screeds and toppings are commonly used as a means of providing smooth
flat floors in residential, commercial and industrial buildings. Toppings
may also be used to increase the structural depth and strength of the
base slab.
The aim of this publication is to provide the information needed by architects,
engineers and contractors for specifying and laying floor screeds and
toppings of acceptable quality. Information is provided on monolithic,
bonded and unbonded screeds and toppings.
2. Definitions
The following definitions are used in this document.
Screed:
A layer of well compacted material, commonly a mixture of cement and fine
aggregate, that is applied to a base at the appropriate thickness and
that has a surface suitable for
receiving a floor finish.
Topping:
A layer of high-strength concrete designed:
a) to provide a dense, abrasion resistant surface on a concrete base,
or
b) to increase the structural depth and strength of a base slab (structural
topping).

Levelling a concrete topping. Reinforcement and temporary screed battens
in the foreground.
3. Specification
3.1 Suitability of screeds and toppings
Screeds are essentially light-duty flooring elements and are suitable
for:
- Wearing surfaces of floors of utility rooms in
domestic premises (e.g. store rooms, garages)
- Floors covered with carpets, plastic tiles or
linoleum, etc and subjected to relatively light traffic such as in offices,
shops and hospitals
Screeds are generally not suitable as wearing surfaces in commercial
buildings, schools etc. or in industrial premises. Preferred methods of
floor construction for such premises are full-thickness trowelled concrete
or a topping on a concrete base.
Screeds and toppings should be specified only where placing and finishing
the concrete floor to acceptable standards is impracticable.
3.2 Surface finish
Screeds
The surface of the screed should be finished according to the type of
wearing surface or flooring that is to be laid. For mastic asphalt, wood
block and strip, and some textile floor coverings, a non-slip finish is
appropriate, while thin sheet and tile floor coverings usually require
a smoother, steel trowelled surface. If a designer specifies the use of
a thin sheet or tile floor, then the use of a smoothing compound needs
to be specified in certain circumstances.
Toppings
The surface of the topping should be finished to meet the abrasion requirements
of the facility. Guidance is given in Table 3.
3.3 Specifying tolerances in levels and surface regularity
When specifying departure from datum and surface regularity, taking into
account the types and thicknesses of the flooring and the screed or topping,
the designer needs to consider:
- the finished floor surface;
- the screed/topping/direct finished slab surface;
- the base slab to receive a screed or topping.
Figure 1: Deviation from datum level (Exaggerated
vertical scale)

Some variations in surface regularity
can be allowed without detriment to the satisfactory application of the
flooring. The permissible limits associated with surface regularity and
departure from datum depend on many factors. In general, the thinner the
applied flooring the higher the class of surface regularity required.
Maximum permissible departure of the level of the screed or topping surface
from datum and the required class of surface regularity should be included
in the job specifications.
Deviations from datum level (see Figure 1).
Permissible deviation from datum level depends on the area of the floor
and its intended use. For large areas for normal purposes ±15 mm
from datum should be satisfactory. Greater accuracy may be required in
small rooms, along the line of partition walls, in the vicinity of door
openings and where specialized equipment is to be installed directly on
the floor and in the case of high tolerance industrial floors.
Table 1: Classification of surface regularity of floor

Surface regularity
This is described as the maximum permissible deviation from a straight
line 3 m long joining two points on the surface. See Figure 2. Values
of deviation with corresponding class of surface regularity are given
in Table 1.
Figure 2: Deviation from a straight line 3 m long joining two points
on the surface (Exaggerated vertical scale)

The class of local surface regularity of a finish
should be selected from those given in Table 1 according to the use of
the floor. In making this selection, account should be taken of the type
and thickness of the surface or flooring to be applied and the standard
of surface regularity required of the finished floor. The highest standard
(Class 1) should be used where a thin flooring is to be applied and where
the minimum irregularity is required of the finished floor, e.g. for a
television studio. In cases where a very flat floor finish is required,
Class 1 using the straight-edge method, may not be adequate and other
methods may have to be used (see Further Reading number 6). Conversely, the lowest type of wearing surface is applied where the
regularity of the
finished floor is not a significant factor. Insistence on higher standards
of surface regularity than are necessary will result in higher costs.
In service, the suitability of a floor in terms of surface regularity
is governed by its radius of curvature and changes in height over short
distances. Specialist test equipment is
now available with which to access these factors and new specifications
can be used to control them (see Further Reading number 6). Although this new test equipment is more complex to use than the straightedge,
it is less laborious on large floor areas.
The designer should specify the maximum permitted abrupt change in level
across joints in direct finished slabs and screeds and toppings taking
into account the type and thickness of the flooring
to be applied. For some types of floorings, a maximum of 2 mm would be
acceptable, taking into account the surface preparation necessary to receive
the flooring. For other types of flooring, especially thin floorings,
or where no flooring is to be applied, it would be appropriate not to
have any changes in level across joints.
Readings should be taken as soon as possible after completion of the screed
or topping.
Various methods of specifying surface flatness and level-ness are discussed
in Further Reading number 7.
3.4 Specifying the strength of screeds and toppings
Screeds
The strength of a hardened sand-cement screed can be tested with the BRE
screed tester. Specifying an acceptance criterion before the start
of the job is advisable as this could prevent disputes after completion.
The BRE screed tester consists essentially of a mass which
is dropped on a standard foot piece which is placed on the surface of
the screed. See Figure 3.
The indentation resulting from four impacts of the mass is measured and
is an index of screed strength. Acceptance limits for various strength
categories are given in Table 2.
Toppings
A topping should have a characteristic 28-day compressive strength appropriate
to the desired abrasion resistance (see Table 3), or designed compressive
or flexural strength, but of at least 20 MPa where abrasion is not a consideration.
The coarse aggregate used should be of nominal size 6,7 mm for monolithic
toppings of nominal thickness 25 mm and of nominal size not exceeding
9,5 mm for separate bonded
toppings of nominal thickness 30 mm. If the nominal thickness of the topping
exceeds 40 mm, however, the nominal size of the coarse aggregate should
be increased to one-quarter of the thickness of the topping, subject to
a maximum of 19 mm.
4. Types of screeds and toppings
In this publication three types of screeds and toppings are discussed:
- Monolithic screeds and toppings which are applied
to the floor while the concrete in the base is still in a plastic state.
- Bonded screeds and toppings which are applied
to hardened concrete floors.
- Unbonded screeds and toppings which are used when
it is impossible to ensure a good bond between floor and screed or topping.
In this case the screed or topping is separated from the floor by insulation
boards or an impervious membrane.
While all three types have many characteristics in
common, they also differ in some important ways. These are dealt with
in the following sections.
4.1 Monolithic screeds and Toppings
As defined above, these are screeds and toppings that are applied at the
time when the underlying concrete floor is placed. Screed thickness should
be approximately 25 mm but not less than 15 mm or more than 40 mm. The
minimum thickness of a monolithic topping at any part should be 20 mm.
Table 2: Screed-strength acceptance limits using the BRE
screed tester

The actual thickness required will depend on structural
requirements. In some circumstances, the design
thickness of a topping may have to be increased to more than 40 mm, but
then there will be an increasing risk of loss of adhesion to the base,
due to differential shrinkage stresses.
Figure 3: "BRE screed tester

In attempting to achieve good adhesion between screed/topping and base
concrete, it is important to take cognisance of the phenomenon of bleeding
of fresh concrete. Bleeding causes water to accumulate on the top surface
of the fresh concrete and the presence of this water layer may impair
adhesion unless suitably dealt with.
The screed/topping should therefore be laid at one of two stages:
- either immediately the concrete has been compacted
and levelled off and before bleed water appears on the surface (immediate
placing);
- or after bleeding of the concrete has ceased and
bleed water has evaporated or has been removed completely by mopping
up (delayed placing).
Immediate placing requires
careful timing but has the advantage that no preparation of the concrete
surface is required.
Timing of delayed placing is not as critical but the surface
of the concrete does require some preparation: laitance should be loosened
by light brushing, with a wire brush or a brush with stiff bristles, and
thoroughly removed by sweeping, or preferably, by vacuum cleaning. Delayed
placing should however be done within an hour or two after the end of
the bleeding period.
4.2 Bonded screeds & toppings
As defined previously, bonded screeds and toppings are applied to hardened
concrete. The hardened concrete is also known as the base concrete.
Screed thickness should be not less than 25 mm or more than 50 mm. The
minimum thickness of a bonded topping at any part should be 35 mm. The
actual thickness required will depend on structural requirements. In some
circumstances, the design thickness of a topping may have to be increased
to more than 60 mm, but then there will be an increasing risk of loss
of adhesion to the base, due to differential shrinkage
stresses. In these circumstances, the use of a reinforcing mesh (ref.
193 or 245) as close to the upper surface as is permissible will assist
in restraining differential shrinkage and in controlling cracking.
Base-concrete requirements
The concrete on which the screed or topping is to be laid should be hard
and strong (i.e. characteristic strength of at least 20 MPa). Weak, friable
concrete is not suitable as a
base for a screed or topping as the achievement of adhesion between such
material and the screed or topping is not possible.
The base concrete should be free of random cracking. Floor screeds or
toppings are unable to bridge over cracks in the base and such cracks
will in time reflect through the screed or topping.
Table 3: Classification of abrasion resistance recommendations
for concrete finishes

The surface of the base concrete should be reasonably
accurate to the required level so that it is possible to place the screed
or topping to a uniform thickness.
Preparing the base concrete
The base concrete should be prepared in such a way that it is left with
a surface that is uniformly hard, clean, and free of dust, oil or other
contamination.
Any screeds or toppings applied previously to the base should be removed
completely.
The laitance on the base concrete should be entirely removed by mechanical
scabbling or scarification in order to expose cleanly the coarse aggregate.
All loose debris, dirt, and dust should be removed using vacuum equipment.
These operations should be delayed until shortly before the screed or
topping is laid, in order to prevent any contamination or accumulation
of dirt.
Bonding of screed or topping to base
The use of a sand-cement grout, if properly applied, should give good
results and is described below. (If a proprietary bonding agent is used,
it should be applied strictly in
accordance with the manufacturers instructions.)
The grout should consist of equal volumes of fine, clean sand and loose
cement mixed thoroughly with sufficient water to achieve a consistence
similar to PVA paint. It must be stirred continuously, and used within
30 minutes of making.
The day before laying of the screed or topping is to start (or earlier)
the base concrete should be tested for absorptiveness by pouring about
a cupful of water onto the surface.
If, during the next few minutes, it is clear that water is being absorbed,
the suction of the concrete should be regarded as being high. In that
case the procedure is:
a) Wet the area on which the new screed or topping is to be laid and
keep it wet for four hours or more.
b) Remove all free water on the surface.
c) Allow the surface to become visibly dry so that the base achieves
a saturated surface-dry condition.
d) Apply the grout to the surface.
On the other hand, if the test water is not visibly
absorbed by the concrete during the first few minutes after application,
the suction of the concrete should be regarded as being low and the grout
may be applied to the dry concrete. Concretes with 28-day characteristic
strengths of 25 MPa and over, if properly compacted and cured, can be
regarded as non-absorptive. In such cases, toppings have been successfully
applied without a bonding grout provided the surface is clean and adequately
prepared.
The grout may be slushed over the area where it is needed, but must then
be worked thoroughly into the surface of the concrete by scrubbing with
brushes and then brushed out to leave only a thin coating on the concrete
without pools of grout in depressions. The brushes used for grouting should
have bristles about 60 to 100 mm long and flexible enough to reach down
into all the irregularities of the surface of the concrete. (Stiff carpet
brushes are suitable, as are some garden brooms provided the base concrete
is sufficiently even. Bass or yard brooms are not suitable because their
bristles are too stiff and too close together. Hair brooms
are too soft to be effective.)
Because the screed or topping mix must be laid on the grouted surface
while the grout is still visibly wet, i.e. within 10 to 20 minutes of
applying the grout, grouting must be
done over small areas at a time, just ahead of laying of the screed. The
grout must be made up in small quantities at a time, as needed.
NOTE: Under no circumstances should the grout be allowed to dry out
before placing the screed/topping as this will cause debonding. If there
is any doubt about the possibility of a delay occurring, it is better
to omit the grouting operation.
4.3 Unbonded screeds and Toppings
Screeds
Where screeds are, or have to be laid on a damp-proofing membrane or separating
layer, the minimum thickness of the screed should be at least 50 mm. Where
they are laid on a compressible layer, such as insulation boards, the
minimum thickness should be at least 70 mm.
Topping
Where a concrete topping is required over a damp-proof membrane, an unbonded
overlay of minimum thickness 100 mm should be used in order to minimise
the risk of curling. The grade of concrete for a direct-finished overlay
should be in accordance with Table 3.
A similar unbonded overlay should be used where a base has become contaminated
(e.g. with oil), and bonding is not possible.
The concrete used for an overlay intended to support a high-strength concrete
topping should have a 28-day compressive strength of at least 35 MPa.
5. Screeds in general
5.1 Materials for screeds
Sand
The quality of the sand, i.e. its concrete-making properties, has a large
influence on the quality of the resulting screed. It should be a concrete
sand not a plaster sand but the largest particles
should be removed by sieving the sand through a sieve with openings about
5 mm wide to facilitate finishing.
Where possible, the sand should be tested in a laboratory beforehand.
It should then, in a mix of 3,5 parts of dry sand and 1 part of cement
by mass, produce a plastic, easy-working, cohesive mortar of plastering
consistence (i.e. a slump of about 40 mm) with a water content per cubic
metre of not more than 320 l but preferably not more than 300 l.
(The higher the water requirement, the lower
the strength of the hardened screed and the greater the drying shrinkage
and tendency to crack.)
To produce a mix that is easy to finish to a smooth surface, it may be
necessary to blend two or more sands. Commonly a blend consisting of 4
parts of crusher sand, sieved as above, and 1 part of a clean plaster
sand, gives good results.
NOTE: Sieving must be done on horizontal sieves which are shaken, or
on cylindrical sieves which are rotated. The practice of throwing the
sand onto a sloping sieve with a shovel is unacceptable because it is
inaccurate, unreliable and wasteful.
Cement
Use cement complying with SANS 50197-1 type CEM I or CEM II A. To use
other cements, first obtain expert advice.
Admixtures
Commercially available admixtures, especially of the water-reducing type,
may be used, but preferably only on the recommendation of the laboratory
which tests the sands, and only where adequate control of dosage on site
can be guaranteed.
5.2 Batching
Mix proportions should be:
Sand, measured in the moist, loose state: 130 l
Cement: 50 kg
Water: sufficient to achieve a plastic, workable consistence.
The capacity of a builders wheelbarrow is 65 l so batches consisting
of two barrowloads of sand and one bag of cement are convenient for mixing
by hand or in a sufficiently large concrete mixer. The volume of compacted
screed mix produced by such a batch is approximately 115 l.
Smaller batches may be made up as follows:

The size of the batch should never exceed the amount
that can be used up within 45 minutes of mixing.
Apart from wheelbarrows, containers such as buckets, boxes or drums of
known volumes may be used for batching. Batching containers should always
be filled flush to the rim. Sufficient containers for a complete batch
should be provided to avoid the possibility of errors in counting.
5.3 Mixing
Machine mixing is preferable and each batch should be mixed for not less
than three minutes if this method is used. With hand mixing, the sand
and cement should be mixed
without adding water until the colour is uniform. Then only may the water
be added, the quantity used being just sufficient to produce a mix of
the desired consistence. Hand
mixing should be carried out with shovels on a smooth concrete floor or
a steel plate.
Mixing directly on the ground should not be permitted as this results
in contamination of the mix with earth and/or organic matter.
5.4 Placing and compacting
Control of levels
Narrow strips of screed mix, laid 3 to 4 m apart and compacted to finished
level, should be used as guides to establish the level of the screed.
The screed should be placed and compacted immediately after laying the
guide strips.
Where the edge of a guide strip forms a daywork joint it should be formed
or cut to produce a vertical joint. Alternatively, and especially for
bonded screeds, timber or metal screed battens, carefully levelled and
trued, should be fixed at the correct height for the required thickness
of screed. At daywork joints all bedding screed beneath the battens should
be cut away to form a vertical joint.
Panel sizes and joints
Screeds should be laid in areas as large as possible in one operation,
consistent with achieving acceptable surface regularity and the levels
required, to minimise the number of joints. Although screeds laid in large
areas may crack at random intervals as they dry and shrink, these cracks
are more acceptable than the curling which may occur at vertical butt
joints if screeds are laid in small panels.
Where joints are present in the base concrete, they should be continued
through the screed so that joints in screed and base line up exactly.
Where screeds are placed on precast concrete elements this may not be
practicable. In such cases, the use of a reinforcing mesh in the screed
may be used to control cracking of the screed and applied floor finishes,
along joints between precast units, provided panel sizes do not become
excessive. This is particularly important if the applied finishes are
brittle, or the slab is subject to external influences, such as thermal
stresses, which could cause movement.
Joints may be formed with screed battens if screeds on each side are cast
at different times, or by cutting through the partially stiffened screed
mix with the edge of a trowel before the screed sets if both sides are
laid at the same time. If the screed is not to be covered subsequently,
edges at joints should be rounded to a 3 mm radius.
Time Limits
The time which elapses between the start of mixing a batch and when that
batch is placed and compacted should not exceed 45 minutes, and during
that time the mix should be protected from drying out.
Batches not placed and compacted within this time, or which have stiffened
to a degree that their workability (consistence) cannot be restored fully
by turning them over a couple of times with spades, should be discarded.
Consistence of the fresh mix and means of compaction
It is essential that, during laying, the fresh mix be compacted fully.
The consistence of the fresh mix and the means of compaction must therefore
be matched to ensure that this is achieved. Generally therefore the fresh
mix should be nearly as soft and plastic as a cement plaster (slump about
40 mm).
Spreading and compacting can then be done with relatively light timber
screed boards operated by one or two workmen.
The screed mix should be dumped on the base concrete (freshly grouted
in the case of bonded screeds) and spread somewhat thicker than the final
required thickness. It should then be compacted using a screed board with
a vertical chopping motion. Extra compaction with hand tampers is recommended
along the edges of panels and adjacent to screed strips.
Once the screed has been compacted it should be taken to the correct level
with a screed board riding on the screed strips or battens (or side forms
in the case of monolithic screeds). The surface can then be woodfloated
to remove any ridges made by the screed board.
NOTE: The use of stiff semi-dry mixes, laid with light screed boards,
is a particularly common cause of weak screeds because such mixes are
not adequately compacted. Semi-dry mixes can however produce very superior
screeds, but only if they are compacted by power operated equipment such
as vibrating screed boards and the consistence is correct.
6. Toppings in general
6.1 Materials
Aggregates
Aggregates for concrete should comply with the requirements of SANS 1083.
The coarse aggregate should be of nominal size 9,5 mm for topping of nominal
thickness
30 mm. However, if the nominal thickness of the topping exceeds 40 mm,
the nominal size of the coarse aggregate should be increased to one quarter
of the thickness of the
slab, subject to a maximum of 19 mm.
Cement
Cement should comply with the requirements of SANS 50197-1. Cement extenders
should comply with the require-ments of SANS 1491. The choice of appropriate
cement type depends on the type of floor and the environment in which
it is to be used. Of prime concern are adequate early strength for cutting
of joints and adequate abrasion resistance. In floors with sawn joints,
concrete has to achieve a certain strength to enable sawing of the joints.
With mixes of low early strength, the time taken to reach this strength
is increased. The longer the period between casting and sawcutting, the
greater the possible moisture loss from the concrete and the higher the
risk of shrinkage cracks occurring before the concrete can be sawn. Cement
types and/or cement contents promoting sufficient early strength for sawing
should be chosen.
Because floors have a large surface-to-volume ratio they are prone to
rapid surface drying with the attendant loss of abrasion resistance at
the surface. Effective curing is
therefore essential.
Concrete made with cements having a low early strength or site blended
cements may require adjustments in the concrete mix design to ensure adequate
early strength for cutting of joints, particularly in cold environments.
Curing methods and regimes may also have to be improved to ensure adequate
abrasion resistance, especially in adverse weather.
Admixtures
Commercially available admixtures, especially of the water-reducing type,
may be used, but preferably only on the recommendation of the laboratory
which tests the sands, and only where adequate control of dosage on site
can be guaranteed.
6.2 Mixes
A topping should have a characteristic 28-day strength appropriate to
the desired abrasion resistance (see Table 3), or designed compressive
or flexural strength, but of at least 20 MPa where abrasion resistance
is not a consideration.
6.3 Laying
After screed battens surrounding the panels on which the topping is to
be applied have been attached to the prepared base and the bonding agent
has been applied as described above, the topping should be spread, compacted,
screeded and bull floated as for a concrete floor.

Pumping a concrete topping onto precast flooring.
Reinforcement and screed battens in foreground.

Concrete topping being placed on a
precast floor.
Panel sizes and joints
Monolithic toppings
Monolithic toppings should be laid in panels of the same size as those
of the base.
Full-depth isolation joints should be formed in monolithic toppings against
walls, columns and other fixed objects. Such joints should have the same
width as those in the base, but not less than 20 mm.
Other joints in monolithic toppings should coincide with those in the
base, be of the same type and width as those in the base and extend through
the full depth of the topping.
Bonded toppings
For separate bonded toppings the area of a panel should not exceed 9 m2.
This may not be practicable for structural toppings on precast units where
joints across the span within the central two-thirds of the span cannot
be permitted. This may be overcome by the use of reinforcement as discussed
later in this section. The general pattern of panels will depend upon
such aspects as the shape of the floor area and the position of columns.
Wherever possible, panels should be square, and the length of a panel
should be limited to 1,25 times its width to reduce the tendency to crack.
Full-depth isolation joints should be formed in separate bonded toppings
against walls, columns, and other fixed objects. Such joints should have
the same width as those in
the base, but not less than 20 mm.
Except where intermediate joints are required in the topping to divide
it into smaller panels than the base, joints in separate bonded toppings
should coincide with those in the base, be of the same type and width
as those in the base and extend through the full depth of the topping.
Intermediate joints dividing the topping into panels of recommended maximum
dimensions should be either sawn contraction joints that extend halfway
through the thickness of the topping, or butt construction joints.
Where bonded toppings are placed on precast concrete elements and the
above recommendations are not practicable, the use of a reinforcing mesh
close to the top
surface of the topping may be used to control differential shrinkage and
cracking of the topping and applied floor finishes along joints between
precast units, provided panel
sizes do not become excessive. The larger the panel size and the thicker
the topping, the greater is the amount of steel required.
Unbonded toppings
The maximum panel size of a separate unbonded overslab should be based
on the following rules:
- Maximum joint spacing not to exceed 30 times overslab
thickness, or 4,5 m, whichever is the lesser
- Length-to-width ratio of panels not to exceed
1,25
Full-depth isolation joints should be formed in a
separate unbonded overslab against walls, columns and other fixed objects.
Such joints should have the same width as those in the base, but not less
than 20 mm.
Other joints should be either sawn contraction joints that exceed a depth
of one quarter of the slab thickness, or keyed construction joints. Both
types of joint should be offset at
least 300 mm from those in the base.
Time limits
The time which elapses between the start of mixing a batch and when that
batch is placed and compacted should not exceed 45 minutes, and during
that time the mix should be protected from drying out.
Batches not placed and compacted within this time, or which have stiffened
to a degree that their workability (consistence) cannot be restored fully
by turning them over a couple of times with spades, should be discarded.
7. Finishing
The resistance to wear of a concrete finish is significantly influenced
by the method of finishing and the care with which finishing is carried
out. Under no circumstances should
cement or a dry cement-sand mixture be sprinkled directly onto the surface
of a finish in order to absorb bleed water or laitance, since defects
such as surface scaling may occur later. Surface water should not be trowelled
back into the finish and, similarly, water should not be applied between
trowelling operations, since this may cause surface weakness.
Three types of surface finish are described below, the choice being made
according to circumstances.
7.1 Ordinary non-slip
The surface is left as finished with wooden floats, except that if it
is too open or too coarse it may be given a few passes with either perspex
or aluminium floats to close the surface without smoothing it. Over-working
should be avoided.
7.2 Steel-trowelled
If a hard, smooth finish is required, the surface will have to be steel-trowelled,
using the delayed trowelling method.
After the screed or topping has been spread, compacted and screeded to
level, it should be bull floated.
Bull floating should immediately follow screeding and should be completed
before any excess moisture or bleed water is present on the surface. The
purpose of bull floating is to eliminate ridges and fill voids resulting
from straightedging.
Before further steps are taken, the finish should be left undisturbed
(the delay period) until bleeding has ceased, the surface has stiffened
to the extent that a footprint will barely show, and surface water has
either evaporated or been removed.
Following the delay period, the finish should be floated again.
The purpose of floating is
a) to depress large aggregate below the surface,
b) to remove slight imperfections, lumps and voids and to produce a
level or plane surface, and
c) to compact the finish and consoli-date mortar at the surface in prepa-ration
for other finishing operations.
Floating and trowelling may be carried out by hand
or mechanically. When floating is done mechanically, either a disc-type
float or a trowelling machine with float shoes attached should be used.
Trowelling should be done immediately after floating. The purpose of trowelling
is to produce a smooth, hard surface. For the first trowelling, the trowel
blades should be kept as flat against the surface as is practicable. As
the surface stiffens, each successive trowelling should be made with smaller
trowels tilted progressively more to increase the compaction of fines
at the surface, giving greater density and more wear resistance.
The resistance to abrasion increases with the number of trowelling operations
and the care with which they are carried out. The operations should be
timed to prevent an
excess of laitance being produced at the surface. For the highest abrasion
resistance, final trowelling should be made when considerable pressure
is required to make any
impression on the surface. However, excessive trowelling at this stage
should be avoided, to prevent a polished or slippery surface.
7.3 Finishes that are not to be exposed to severe service conditions
The finish (after it has been spread, compacted, screeded to level, and
floated) should be left undisturbed until bleeding has ceased and the
finish has stiffened to the extent that a footprint will barely show.
Surface water should then be removed from the surface, floated and steel-trowelled
at intervals until the desired texture is achieved.
The texture of concrete finishes can be varied from a fine matt to a glossy
surface, depending on the number of trowellings applied. A coarse non-slip
texture may be produced by brushing a freshly floated surface with a broom,
but the resulting ridges may become subject to abrasion.

Power floating a screed.
Trowelling too soon and over-trowelling should both
be avoided, since they bring to the surface a thin layer rich in cement,
which tends to craze and release dust particles.
8. Curing
Concrete has to be effectively cured if maximum surface strength, maximum
resistance to surface abrasion and low impermeability of the concrete
are to be attained, and the
development of drying shrinkage cracks is to be avoided or minimised.
Effective curing also reduces the effect of differential shrinkage, and
therefore curling, by delaying the
effect of differential drying until the concrete is better able to resist
its effects.
Curing should start as soon after final finishing as practicable, and
should be done by one of the following methods:
a) uniform application of a liquid membrane-forming curing compound
at an approved rate for complete coverage, always taking into consideration
the manufacturers
instructions. Curing compounds should comply with the requirements of
AASHTO M148 and should be of type 1-D or type 2. (This method may not
be suitable where other finishes are to be applied.)
b) ponding
c) covering with thick hessian or similar clean moisture-retaining and
non-staining material that is kept wet
d) covering with polyethylene or similar vapour-proof material in large
sheets, sealed at the edges of the finish and at the side laps of the
sheeting
To prevent surface damage to trowelled and other finishes,
it may be necessary to suspend the coverings described in (c) and (d)
above, clear of the surface until such time as they can be placed directly
onto the surface. Care should be taken to prevent wind tunnelling under
coverings.
Curing should continue for at least 7 days. In cold weather, this period
should be extended. Cold weather may be deemed to be conditions in which
the average ambient temperature falls below 10°C, where
average is defined as the arithmetic mean of the maximum and
minimum ambient temperatures recorded on site within a period of 24 hours.
During cold weather, the curing period should be extended by 0,5 days
for each day in which the average ambient temperature falls to between
5°C and 10°C, and by 1 day for each day in which the average ambient
temperature falls
below 5°C.
9. Material quantities
9.1 Screed
The net approximate quantities of materials required to manu-facture 1
m2 of compacted screed mix 25 mm thick are:
Sand in moist, loose state: 28 l
Cement: 11 kg
An allowance of 10% over and above these quantities
should be made for wastage.
9.2 Grout
For bonded screeds, allow about 1 kg of cement and 1 l of plaster sand
per m2 of screeded area for the grout.
10. Inspection and testing of toppings and screeds
10.1 Inspection
Before the finishing work is started, the base should be checked for any
departure from level, to ensure that the minimum thickness of finish can
be applied.
The work should be inspected during progress and after completion, attention
being paid to the following points:
a) materials
b) preparation of the base, where the finish is to be bonded
c) batching and mixing
d) proper compaction
e) correct finishing
f) correct curing
g) making and curing cubes (see SANS 5861-3:1994) from both topping
and screed mixes
10.2 Testing of the completed work
After completion of the work, the following tests should be carried out:
a) levels and surface flatness of toppings and screeds
b) adhesion of bonded screeds and toppings to the base
c) curling and lipping of unbonded screeds
d) soundness of bonded and unbonded screeds
e) testing (see SANS 5863:1994) of cubes
Levels and surface flatness
Deviation from datum may be checked with conventional survey instruments.
The testing of surface regularity will depend on the type of specification
used. It may be tested by straightedge, precise levelling or other specialised
equipment.
A straightedge at least 3 m long can be used to check surface regularity.
It should be supported on two rigid blocks of identical height (say 15
mm) placed 3 m apart on the
screed surface. Deviations of the screed surface from the straight line
joining the points at which the blocks are placed may measured with suitable
slip or feeler gauges.
Alternatively, specialist methods may be used (see Further reading number
6).
Adhesion between separate bonded toppings or screeds and a base
The adhesion between the topping or screed and the base should be examined
by tapping the surface with a rod or a hammer, a hollow sound indicating
lack of adhesion.
Tests to check the adhesion of a screed or topping
to its base should be made as late as possible in the construction programme
when the maximum effect of drying shrinkage has taken place. Account should
be taken of the time for any replacement sections of screeds and toppings
to be laid within the construction programme.
Curling and lipping of toppings and screeds
Toppings and screeds should be considered unsatisfactory if they have
lifted by a visible or measurable amount at joints and cracks, to the
extent that there is a risk of fracture under imposed loads.
Strength
Screed
The BRE screed tester(see Figure 3) is used to assess strength
once screeds are at least 14 days old and have dried out. No less than
three tests should be carried out in
each area less than 20 m2 and on each 20 to 25 m2 of screed laid in larger
areas. Corridors should be tested at 3 to 5 m intervals.
Test positions should be selected at random, but vulnerable areas adjacent
to panel joints and any shrinkage cracks, and in doorways, should be tested.
Where test indentations exceed those given in Table 2, additional tests
should be carried out to determine the zone of non-compliance.
Test procedure is as follows:
a) Select a sensibly flat, smooth area of screed and remove all loose
dirt and grit.
b) Use the template supplied with the tester to mark the test position
of the feet of the depth-measuring device and take the zero reading.
c) Locate the foot piece of the screed tester at the test position in
contact with the screed.
d) With the guide rod held vertically, deliver four successive blows
of the mass to the foot piece at the same position on the screed, dropping
the mass freely from the trigger
point each time.
e) After the fourth blow, measure the depth of the final indentation
in the screed with the depth measuring-device.
Topping
The BRE screed tester is not suitable for use on high-strength
concrete toppings. The strength of such toppings is determined by testing
cubes taken at the time of laying, or by tests performed on samples taken
from the finished topping.
Assessment of cracks and curling
Cracks should be assessed in relation to the area involved and the flooring
to be applied, and likely future movement.
Fine cracks are not normally detrimental to any applied flooring and do
not need filling: wider cracks may need filling or other remedial work.
Loss of adhesion does not necessarily mean that the screed or topping
is unsatisfactory. It may, however, be critical in the case of structural
toppings.
Those areas of the screed or topping that are considered to be unsatisfactory
should be isolated by sawing, removing and re-laying. Care should be taken
to minimise the effect
that any cutting-out operations may have on the adhesion of adjacent parts
of the screed.
An alternative method that is less disruptive and may be suitable in some
circumstances, is by injection of a low-viscosity epoxy resin into the
crack and the gap under the screed or topping. This operation must, however,
be carried out by a specialist.
11. Further reading
- SABS 0109-2:1992, Code of practice for concrete
floors. Part 2: Finishes to concrete floors, Pretoria: South African
Bureau Standards, 1992.
- SABS 0155:1980, Code of practice for accuracy
in buildings, Pretoria: South African Bureau Standards, 1980.
- SABS 1200-G:1982, Standardized specification
for civil engineering construction. G: Concrete (structural), Pretoria:
South African Bureau Standards, 1982.
- Roberts, R.F. Testing cement-sand screeds using
the BRE screed tester, Wexham Springs: Cement and Concrete Association,
1986. (C&CA Guide 48.057).
- BS 8204:Part 1:1999, Screeds, bases and in-situ
floorings. Part 1: Concrete bases and cement sand levelling screeds
to receive floorings - code of practice, London: British Standards
Institution, 1999.
- The Concrete Society, Concrete industrial ground
floors: a guide to their design and construction, 2nd ed. Slough:
The Society, 1994. (Technical Report no. 34).
- Rogers, M.R. and Barnbrook, G. Concrete industrial
ground floors: Specification and control of surface regularity of free
movement areas. Supplement to the Concrete Society Technical Report
no. 34, Slough: The Society, 1997.
- Marais, LR and Perrie, BD. Concrete industrial
floors on the ground, Midrand: Portland Cement Institute, 1993.
- BS 8204:Part 2:1999, Screeds, bases and in-situ
floorings. Part 2: Concrete wearing surfaces code of practice,
London: British Standards Institution, 1999.
Cement &
Concrete Institute
PO Box 168, Halfway House, 1685
Tel (011) 315-0300 Fax (011) 315-0584 e-mail info@cnci.org.za website
http://www.cnci.org.za
Published by the Cement & Concrete Institute, Midrand, 2002 reprinted