Concrete Strip Roads for the farm
1.
Introduction
Economical and durable all-weather roads, especially suitable for farms
and rural areas, can be made with concrete strips laid as wheel-tracks.
Such roads have proved themselves in many countries. In Zimbabwe for example
they gave excellent service over many years even on provincial-class routes
carrying fast
traffic.
These roads can be built without expensive or sophisticated equipment
and by comparatively unskilled labour that has received a little instruction.
The work can be done in short lengths as labour is available. Strip roads
are a particularly useful means of making steep farm roads passable in
all weathers.
2. Design
Dimensions
Except long curves (where strips should be widened as required), strips
600 mm wide and 1 500 mm apart, centre to centre, are recommended, as
shown in Figure 1.
Figure 1: Cross section of road

Wheel tracks should be widened by 100 mm on the inside
of curves and by 150 mm on sharp bends.
In all figures concrete thickness is indicated by T.
The minimum thickness of concrete is as follows:
Maximum vehicle load 3,5 tons (ordinary farm traffic) 120 mm
Vehicle loads up to 5,5 tons 155 mm
Vehicle loads up to 7,5 tons 175 mm
Reinforcement is not necessary in the concrete.

Drainage
The strips should be built with a longitudinal slope of at least 1 in
100 (10 mm in 1 m) to ensure that stormwater will drain off the road.
In addition, longitudinal edge drains should be considered where rainwater
may tend to accumulate on the road, or where steep slopes may cause erosion
of the road shoulders. Such drains should be constructed at least 1 m
from the edge of the strips and an extra width of prepared roadway will
thus be necessary. The roadway should be suitably sloped between the strips
and the edge drains.
Subgrade
All top soil must be removed to a depth of at least 150 mm before the
strips are constructed. The foundation below the concrete strips is called
the subgrade and this must be compacted by using tampers or heavy rollers
until it is firm.
Before excavating the strips, check the ground levels and correct any
irregularities otherwise the strips will follow the undulations of the
natural ground.
If during excavation of strips, soft, wet or unstable areas are detected,
excavate such areas 300 mm deep and replace the excavated material with
well compacted, granular fill.
Formwork
Rough-sawn SA Pine timber 38 mm thick may be used for longitudinal forms
as follows:

The forms are placed on edge and prevented from moving sideways
by metal or wooden stakes driven into the ground no more than 1 m apart.
Forms for curved track can be made from strips of 6 mm hardboard or plywood
that is suitably bent and held in position with stakes. Transverse forms
should be of planed timber and have strips of wood nailed to them to form
the keyways
(Figure 3).
Joints
Each strip must be divided into panels by transverse grooved or keyed
joints (see Figures 2 and 3). The spacing of these joints is 1,5 m.
Figure 2: Longitudinal section through road showing grooved joint

Grooved joints are used where the strips are placed in a
continuous operation in lengths considerably greater than 1,5 m. Keyed
joints are used in the so-called alternate-panel
method of construction, ie the first, third and fifth panels, etc, are
placed on the first day, and the in-fill second, fourth and sixth panels
on the second day, etc. Where continuous
placing with grooved joints is interrupted for more than an hour, a keyed
joint is required.
Concrete
Use the following materials:
- Cements complying with SANS 50197-1 are recommended.
- Water any water that is fit to drink
- Sand the size of particles should range
from about 5 mm to dust
- Stone crushed stone or pebbles about 20
mm in size.
To make the concrete, mix 1 bag (50 kg) of cement with 65
l of sand, 65 l of stone and enough water to make the con-crete workable
and easy to compact by tamping. (There
are 1 000 l in a cubic metre; the capacity of a builders wheelbarrow
is 65 l). Do not add more water than is necessary as this will weaken
the concrete.
For steep slopes the water content of the concrete mix should be reduced
to prevent it from flowing downhill during compaction.
Mixing must be done by machine or by hand on a concrete floor or other
smooth, clean, non-absorbent surface.
The volume of concrete produced by the above quantities will be sufficient
to place a strip 600 mm wide x:
120 mm thick x 1,7 m long, or
155 mm thick x 1,4 m long, or
175 mm thick x 1,2 m long,
all without anchors.
Figure 3: Longitudinal section through road showing keyed joint
Construction on steep slopes
Where strips are to be constructed on slopes steeper than 1 in 30 (33
mm in 1 m), the strips must incorporate panel anchors and anchor blocks
in accordance with Table 1. The panel anchors and anchor blocks prevent
the completed strips from creeping downhill; details are shown in Figures
4 and 5.
Figure 4: Panel anchor
Figure 5: Anchor block

Panel anchors and anchor blocks are the same width
as the strips. The recesses in the subgrade to form the panel anchors
should be excavated shortly before the concrete is cast.
At the end of a strip road, the last panel should be thickened as in Figure
6, unless it is an anchor block, to prevent damage by traffic.
Figure 6: Panel at end of strip road

Table 1: Provision of panel
anchors and anchor blocks in roads on steep slopes

3. Construction
Placing and compaction
The subgrade under the concrete must be damped ahead of concreting to
prevent water being drawn out of the fresh concrete. However, any free
surface water should be
removed before concrete is placed.
Either the continuous or alternate-panel method
of construction may be used. A screed board should be used to compact
the concrete fully by tamping and to level it off.
The screed board may be a piece of timber 38 mm x 100 mm x 800 mm long,
which slides on the top of the formwork. It is first used with a chopping
action to compact the concrete which should initially slightly over-fill
the formwork; it is then used with a sawing motion to level off the concrete
flush with the top edges of the forms.
For steep slopes where relatively stiff concrete will be necessary, consideration
should be given to the use of a vibrating screed board for compacting
the concrete. This consists essentially of a timber (or steel) member
which can span across the forms and which has a vibrator attached to it
at about mid-span. Only a small motor possibly 100 to 200 W
is required. A poker vibrator would also be satisfactory. But if vibratory
equipment is not available, it must be accepted that a fair amount of
physical effort on the part of the laying gang will be needed to compact
the concrete.
To make a grooved joint, a steel blade, about 3 mm wide and as long as
the strip is wide, is forced down into the concrete to the depth of the
groove required (see Figure 2). The blade is best worked into the concrete
by attaching a vibrator to it. It is then withdrawn leaving a groove into
which is dropped a strip of bituminous roofing felt (eg Malthoid)
cut to size. Surface finishing of the concrete can then be completed.
Surface finishing
Normally and especially if the sand used for the concrete has an
adequate proportion of fairly coarse particles a satisfactory non-slip
finish will be obtained simply by wood floating the concrete as a final
operation. However, on steep slopes, or if the sand is rather fine, or
the mix is rather fatty, it may be better to finish the concrete,
1 to 2 hours
after placing, by lightly brooming it transversely to the direction of
travel so as to produce a multitude of fine grooves across it. Deep texturing
is not required.
Protection and curing
It is essential that concrete be prevented from drying out. If there is
any delay between placing and finishing the concrete, it needs to be protected,
especially in windy weather. Covering with plastic sheefing is recommended
until finishing occurs. For concrete to develop the required strength
it should be kept damp for an adequate period after placing. Damp-curing
should be continued for at least 10
days in warm weather and 14 days in cold weather. The curing procedure
recommended is to cover the work, as soon as surface texturing is complete,
with plastic sheeting that is kept in place with a thin layer of sand
or soil over it and stones along the edges.
Opening to traffic
Full design loads should not be imposed on the concrete until it is at
least 14 days but preferably 21 days old.
On the other hand, provided that they do not interfere with the damp-curing
process, light vehicles such as cars and light trucks (½ ton rated
capacity) can use the strips after 3 days of curing, and trucks of 1½
ton capacity can use them after 7 days of curing.
These restrictions can substantially affect planning of work, as construction
traffic eg trucks carrying aggregates for concrete commonly
provide wheel loads that exceed
those that the strips will be called upon to carry in normal service.
Cement &
Concrete Institute
PO Box 168, Halfway House, 1685
Tel 011 315-0300 Fax 011 315-0584 e-mail info@cnci.org.za
website http://www.cnci.org.za
Published by the Cement & Concrete Institute, Midrand, 1997, reprinted
1999, 2001, 2003,2007
©Cement & Concrete Institute
|