|
WHAT
IS TILT-UP CONSTRUCTION?
The term “tilt-up” describes a
method of constructing concrete walls rapidly and economically. Wall
panels are cast horizontally on the floor slab. After they have
attained sufficient strength, a mobile crane lifts the panels up and
sets them on a foundation. The erected panels are temporarily braced
while the roof and upper floor framing is constructed.
Tilt-up concrete is most commonly used for one to three story
buildings, but its use in multi-story low-rise office and warehouse
buildings is growing. This process offers architects almost unlimited
freedom to arrange and assemble panels, plus a wide choice of surface
finishes. Techniques continue to evolve with new research and
innovations, furthering the advantages of tilt-up construction.
HILLFOX POWER
CENTRE - Johannesburg (1995)
ARCHITECT
MDS Architecture |
CONSULTING
ENGINEER
Ellmer Partnership Inc now part of WSP Structures Africa (Pty) Ltd |
CONTRACTOR
Murray and Roberts |
QUANTITY
SURVEYOR
Norval Wentzel Sreinberg |
SPECIALIST
SUB CONTRACTOR FOR
THE TILT-UP
Tilt Up Systems |
|
DESCRIPTION
The 36 500 m2 Hillfox Power
Centre, constructed in Roodepoort in 1995, represented a new concept in
high-volume value shopping in South Africa.
From the outset, during the preliminary planning phase of this project
it was recognized that the size of the project, the stipulated 10 month
construction period as well as other considerations, called for new
innovative thinking in terms of design and detailing for rapid, simple
and economical construction, within the framework of architectural,
cost and erection constraints.
Due to the repetitive and extensive yet interesting nature of the
façade, tilt-up construction was a natural alternative to an
in-situ concrete frame and brickwork façade solution.
REASONS FOR TILT-UP ALTERNATIVE
At a very early stage of this
project it became clear that the relative complexity of the
façade element was a potential drawback in terms of cost and
construction time on this fast track project. In addition several other
considerations enter the equation.
-
The brick wall/concrete
frame interface often leads to undesirable cracking and necessitate the
introduction of plaster joints at this interface.
-
Plaster cracking is
always a potential danger and is often unpredictable and difficult to
remedy should it occur.
-
The relative slowness of
brickwork to such complicated facades was a distinct drawback.
-
Approximately 2000
linear meters of façade was to be built in-situ in a
construction period of only 10 months.
-
Tilt-Up Construction
lends itself well to the repetitive nature of the proposed facades.
The painted finish required by
the Architect could easily be obtained by simply painting the smooth
off-shutter finish of the panels, therefore eliminating the important
wet trade of plastering.
A full alternative design in
Tilt-Up Construction technology was tabled and this indicated a
potential cost saving of approximately 17% against the conventional
solution and a saving of approximately 10% in construction time.
back to top^
GATEWAY SHOPPING
CENTRE - Umhlanga Rocks (1999)
OWNER
Old Mutual Properties
|
ARCHITECT
Johnson Murray Architects |
CONSULTING ENGINEER
Tobbell Strech & Associates |
MAIN CONTRACTOR
Gateway Construction JV |
|
SPECIALIST TILT-UP CONTRACTOR
Tilt Up Systems cc |
What is on offer at Gateway?
-
Over 375 shops and
restaurants,
-
A skateboard park.
-
Standing wave pools for
surfing and body boarding including the world’s first double point
break.
-
27-m high indoor climbing
wall. (Highest in the world)
-
18 cinemas
-
An IMAX theatre
-
A children’s
entertainment arcade
PROJECT INFORMATION:
Total Size
317 843 m2
Gross Lettable area
126 487 m2
Parking Arcades/ Public areas /
Malls
191 356 m2
Tallest panel
19,7 m
Largest Panel
19,7 m x 5,2
m
Heaviest Panel
4
T
Number of tilt-up elements
357
Total gross area of elements
Over 17 000 m2
WHY TILT-UP?
QUALITY, SPEED, FLEXIBILITY
& COST
The powerfloated finish of the
tilt-up panels was far superior in both quality and durability to the
steel floated finish that would have been attainable with a brickwork
and plaster alternative. Furthermore despite being used only as a
cladding and not as a structural element tilt-up was cost competitive
offering better “value for money” than any other alternative.
Tilt-up was able to achieve the
aesthetic relief features required by the Architects simply and
economically and with an accuracy and quality not possible with any
other construction method.
The speed of erection inherent
in tilt-up construction enabled the contractor to weatherproof the
building six months ahead of schedule thereby allowing more time for
the complex internal finishes required to the internal mall areas
The client requested that the
contractor investigate alternative construction methods to the
conventional brickwork and plaster solution to ensure a “world class
centre”. As a result several options were investigated before
finally selecting tilt-up as the best alternative. Meetings were
held with the professional team to explain tilt-up construction and the
benefits the system could bring to the development as well as to
resolve how tilt-up could meet the specific requirements of the
project. Site visits to completed projects were arranged so that
the team could see examples of the quality of finish attainable.
Before proceeding the client
authorised that a full size mock-up of a corner of the building be
built in order that various details could be tested to ensure that they
worked practically. Four wall panels each about 13m x 5m, a
corner element and two tilt-up columns were formed, cast and
erected. A first floor slab was cast and roof steelwork erected.
The owners then raised concerns
over flexibility and how tilt-up could accommodate changes due to
tenant requirements. The perception was that tilt-up was an
inflexible building method. A report was prepared that looked at
every conceivable change that might be required, from cutting openings
in a panel to removing the entire bottom half of a panel and even the
removal of complete panels.
Tilt-up was able to accommodate
all eventualities and in most instances accommodated the changes better
than either brickwork and plaster or conventional precast. As a
demonstration a door opening was cut into one of the mock-up panels and
a frame and door installed.
Towards the end of the project
tilt-up proved invaluable in accommodating openings that were required
for air conditioning ducts, fire escapes and other services.
Openings were cut in panels that had already received their final coat
of paint and with minimal disruption, mess and touch-up required,
tilt-up met the demands of flexibility with flying colors.
back to top^
GATEWAY –
EDGARS EXTENSION (2004) - GAME
EXTENSION (2007)
OWNER/DEVELOPER
Old Mutual Properties |
ARCHITECT
CHT Architects |
CONSULTING
ENGINEER
Tobbell Strech & Associates |
MAIN
CONTRACTOR
Grinaker- LTA Building East |
SPECIALIST
TILT-UP CONTRACTOR
Tilt Up Systems cc
|
|
back to top^
MAPONYA
MALL - Soweto (2007)
OWNER/
DEVELOPER
Richard Maponya’s Maponya Group and Zenprop Property Holdings |
ARCHITECT
Bentel Associates International |
CONSULTING
ENGINEER
Sotoralis Consulting |
CONTRACTOR
Grinaker-LTA |
SPECIALIST
SUB CONTRACTOR FOR
THE TILT-UP
Tilt Up Systems cc |
|
Background
This upmarket, 70 000-m2
shopping centre, in Klipspruit, Soweto, is scheduled for completion in
September 2007. The reasons that the tilt-up method of construction had
been chosen for this project are cost competitive pricing, quality of
construction, finish and speed of construction.
The mall will feature anchor
tenants that include major national retailers Pick ‘n Pay, Woolworths,
Edgars, Truworths and the Foschini Group, as well as Ster Kinekor
cinemas.
Maponya Mall during
construction
back to top^
UMLAZI MEGA CITY -
Durban (2005)
ARCHITECT
FGG Architects |
CONSULTING
ENGINEER
Young & Satheria |
SPECIALIST
TILT-UP CONTRACTOR
Tilt Up Systems cc |
CONTRACTOR
Grinaker-LTA East |
Background
Umlazi Mega City is the
township’s first ‘sizeable’ shopping centre. In addition to a 28,000-m2
shopping area, it offers a service station, taxi rank, offices and a
motor city.
In the construction of Umlazi
Mega City, Grinaker-LTA utilised ‘Tilt-Up’ technology for the shopping
centre’s external facades. The same method will be used at Maponya
Mall. Explains Cloete: “Tilt-Up will be used for all the external
façade walls at Maponya Mall. The external wall panels, some 8 x
10 m in size, will be cast horizontally on site and then lifted
vertically into position by crane. The design of the anchor positions
is undertaken in the USA, and this, together with the lifting process
itself, requires specialised expertise. The speed of the panel erection
coupled with a quality finish provides an attractive option in a market
where skills are scarce.”
back to top^
SIBAYA
CASINO - KZN North Coast (2004)
OWNER/
DEVELOPER
Afrisun Kwa Zulu Natal |
ARCHITECT
Northpoint |
CONSULTING
ENGINEER
KAYP Consulting Engineers |
CONTRACTOR
WBHO- MEG JV |
SPECIALIST
SUB CONTRACTOR FOR
THE TILT-UP
Tilt Up Systems |
|
2006 Tilt-Up
Achievement
Award Winner ::
Commercial
Division 
Submitted by:
Tilt-Up
Systems
TCA Member Participants
Tilt-Up Systems (Kloof, South
Africa)
Role: Tilt-Up Contractor
Lowden and Associates (Oakland, California)
Role: Consultant
Meadow Burke
(Tampa, Florida)
Products: Bond-Breaker, Lifting Hardware
From the unique architecture
and idyllic setting, to the awe-inspiring Afro-chic atmosphere and the
fantasy world of a state-of-the-art casino, there’s much to experience
in this 2006 TCA award winning project. Featuring over 900 slot
machines and thirty-seven table games, the property is also an elegant
resort with eight restaurants and two hotels with 156 rooms.
Low maintenance, cost-effectiveness and quality made Tilt-Up the
solution for this facility.
The Sibaya Casino is designed around the local Zulu culture. Its
massive central domed structure is encircled by eight satellite
structures with their own identities. The unique façade features
create unusual curved structures with hardly any straight lines. When
the owner wanted to incorporate curved walls even though they had never
been done by the contractor, a full-size sample was constructed to
demonstrate the success of this technique.
Constantly changing levels around the site created a tight space, which
necessitated the creation of bulk earthwork platforms to create space
for casting beds and provide crane access.
In order to create the curved front face of the panels, sacrificial
casting beds were created around the outside of the building. This
process involved casting two level strips of concrete that had steel
bolted onto it to create tracks. A steel strike rail that was shaped to
the radius of the required panel “ran” on these rails. The earth
between the tracks was then shaped and the bed cast and floated using
the strike rail to ensure a constant radius along the height of the
panel.
The panels were not just a constant thickness but also had integral
columns and beams cast into them to create the depth required by the
architect. Panels were cast in a two-phase operation, and certain
panels had battered faces requiring the integral columns to taper so
that once the back face of the column was plumb, the front face of the
panel would slope backwards. Large polystyrene void forms were placed
into the panel before encasing them in concrete to reduce the panel
weight.
To simulate local ethnic building techniques, a dry, granolithic screed
mix was added to the concrete surface and hand floated into the
concrete to create a textured finish. Deep recesses were formed
cost-effectively by creating a composite recess former of polystyrene
with a ply board that could be glued to the casting surface and would
not be damaged during fixing of reinforcing and concreting of the
panels. Beige paint was used to complement the existing landscape.
Judges rated the Sibaya Casino as a favorite because this project
serves as “a genuine iconic milestone for the site-cast concrete wall
panel industry. The shear magnitude and complexity of the scope should
be inspiring to anyone involved with or contemplating using this
construction method…Projects like this start to legitimize Tilt-Up
within the design excellence elitist, which will slowly erode the big
box stigma we currently face with so many non-believers.”
back to top^
FREEDOM TOWERS AT
WALTER SISULU SQUARE - Soweto (2006)
SPECIALIST SUB CONTRACTOR FOR
THE TILT-UP
Tilt Up Systems cc

Freedom Towers
at
Walter
Sisulu Square
2006 Tilt-Up
Achievement Award
Winner :: Special Projects Division 
Submitted by:
Tilt-Up
Systems
Constructed on the center of
the busiest traffic circle in Kliptown, this project had the goal of
creating a complex feature entrance wall to a new National Monument in
Soweto, South Africa.
The owner wanted to ensure no construction joints were visible in the
columns for the Freedom Towers, which was easily achieved with Tilt-Up.
Five of the Freedom Towers columns are made of black concrete with
white aggregate, and four of the columns are made of white concrete
with black aggregate. This represents the new South Africa where black
and white people stand together in harmony.
Large floodlights inside and outside the columns of the Freedom Towers
provide a spectacular illumination at night.
The remarkable monuments caught the eyes of the judges on Walter
Sisulu. Judges cited the use of light, form and special relationships
that serve to create a landmark most observers could never forget.
TCA Member Participants
Tilt-Up Systems (Kloof, South
Africa)
Role: Tilt-Up Contractor
Lowden and Associates (Oakland, California)
Role: Consultant
Meadow Burke
(Tampa, Florida)
Products: Bond-Breaker, Lifting Hardware
Related Award Winning Projects
The purpose of the TCA Awards
Program is to recognize outstanding site cast Tilt-Up structures and
advances in technology, products and methods used in the Tilt-Up
industry.
Quick Facts:
Tallest
Panel:
59' (18 m)
|
Largest
Panel:
635 sqft ( 59 m2 ) |
Heaviest
Panel:
100,000 lbs (45 455 kg)
|
Construction
Time:
60 days |
back to top^
HIRSCH STORE
- Durban (2006)
OWNER
Hirsch Group |
ARCHITECT
Elphick Proome Architects |
CONSULTING
ENGINEER
Slabbert & Associates |
CONTRACTOR
Tilt Up Systems cc |
SPECIALIST
SUB CONTRACTOR
FOR
THE TILT-UP
Tilt Up Systems |
|
REASONS FOR USING TILT-UP
Due to the client’s demanding requirements with regard to security,
fire resistance, insulation and durability (due to the coastal
conditions), the 4000 m2 concrete warehouse has to be the first
warehouse in South Africa that is entirely made up of concrete. The
external perimeter panels, columns and beams were all precast and
lifted into position. The roof system was made up of precast concrete
rectangular shaped beams with polystyrene filler blocks and a concrete
structural topping ( hybrid concrete).
back to top^
LG
ELECTRONIC WAREHOUSE - Pinetown (2003)
ARCHITECT
R&L Architects |
CONSULTING
ENGINEER
A J Smith & Associates |
TILT-UP
CONTRACTOR
Tilt Up Systems cc |
|
REASONS FOR USING TILT-UP
Plaster cracking is always a
potential danger and is often unpredictable and difficult to remedy
should it occur. Other reasons for using tilt-up for the 7500 m2
warehouse/ distribution centre included cost competitive pricing,
quality construction/ finish, speed of construction, security and fire
resistance.
back to top^
CLICKS
DISTRIBUTION CENTRE - Centurion (1999)
CONSULTING
ENGINEER
Arcuss Gibb |
MAIN
CONTRACTOR
Giuricich Bros/ NMC JV |
TILT-UP
CONTRACTOR
Tilt Up Technologies (Pty) Ltd
now under the name of Tilt Up Systems cc |
|
REASONS FOR USING TILT-UP
Plaster cracking is always a
potential danger and is often unpredictable and difficult to remedy
should it occur. The reasons for using tilt-up for the 35000 m2
warehouse included cost competitive pricing, quality construction/
finish, speed of construction, security and fire resistance.
back to top^
ZEVENWACHT
SHOPPING CENTRE - Kuilsriver (2007)
OWNER/
DEVELOPER
Zenprop |
ARCHITECT
Vivid Architecture |
CONSULTING
ENGINEER
Africon (Pty) Ltd |
MAIN
CONTRACTOR
JT Ross- Cape |
TILT-UP
CONTRACTOR
Tilt Up Systems cc |
|
WHY TILT-UP?
QUALITY, SPEED, FLEXIBILITY
& COST
The power floated finish
of the tilt-up panels was far superior in both quality and durability
to the steel floated finish that would have been attainable with a
brickwork and plaster alternative
Tilt-up on the 40,000 m2 retail centre was able to achieve the
aesthetic relief features required by the Architects simply and
economically and with an accuracy and quality not possible with any
other construction method.
back to top^
FUEL GROUP
DISTRIBUTION CENTRE - Durban (2007)
OWNER
Zenprop |
ARCHITECT
Empowered Spaces Architects |
CONSULTING
ENGINEER
DG Consulting Engineers |
CONTRACTOR
Grid Construction |
TILT-UP
CONTRACTOR
Tilt Up Systems cc |
|
back to top^
MR PRICE
DISTRIBUTION CENTRE - Durban (2005)
OWNER
Zenprop |
ARCHITECT
Empowered Spaces Architects |
CONSULTING
ENGINEER
Solotaris Consulting |
MAIN
CONTRACTOR
Stocks & Stocks |
TILT-UP
CONTRACTOR
Tilt Up Systems cc
|
|
back to top^
MERTHYR
HOUSE - Pinetown (1984)
ARCHITECT
ZAI Architects |
CONSULTING
ENGINEER
ZAI Engineers |
MAIN
CONTRACTOR
Inland Constructions Natal (Pty) Ltd |
TILT-UP
CONTRACTOR
Tilt Up Systems cc |
back to top^
DELCLAIM SHOPPING
CENTRE - Kloof (2000)
CONSULTING
ENGINEER
Nick Emery & Associates |
ARCHITECT
R&L Architects |
TILT-UP
CONTRACTOR
Tilt-Up Technologies (Pty) Ltd
now known as Tilt-Up Systems cc. |
|
DESCRIPTION
2500 m2 Retail
back to top^
WELTEVREDEN
SHOPPING CENTRE - Mitchells Plain (1990)
CONSULTING
ENGINEER
Partnership De Villiers |
MAIN
CONTRACTOR
Murray & Roberts – Cape |
TILT-UP
CONTRACTOR
Tilt-Up Technologies (Pty) Ltd
now known as Tilt-Up Systems cc. |
DESCRIPTION
35000 m2 Retail
|