TILT-UP CONSTRUCTION

Tilt Up is without doubt an improved method of construction that has evolved to meet  the changing needs of our industry and in so doing, elevates the construction industry by ensuring:

      • Quality
      • Speed
      • Durability
      • Cost effectiveness
      • Efficient utilisation of available unskilled and semi-skilled labour resources
So what is Tilt Up?
  • Tilt Up can be defined as the on-site casting of large concrete elements that are lifted once by means of a mobile crane, placed in their final position, and temporarily braced until being connected into a unified structure.
  • Unlike precast panels that are generally used as a cladding, a tilt up panel acts as a structural element within the building capable of carrying roof and slab loads.
    
  • The technology generally utilises lifting inserts cast into the face of the elements, thereby drastically reducing erection stresses by spreading the erection loads evenly over the element.
  • Lifting inserts are positioned relative to the centre of gravity of the panel to ensure that the rigging rotates through snatch blocks as the panel is lifted, until it hangs slightly out of plumb once lifted off the ground.
  • Other than the final applied finish, panels require no further finishing as they offer a powerfloated finish to both external and internal faces.
  • A tilt up panel therefore, provides the building structure an envelope and final finish in one operation.



What can be done with tilt up?

Tilt up is an extremely versatile method of construction offering a cost effective solution to many challenges it is presented with. Initially used to create simple wall panels, tilt up has itself evolved to the point where the benefits of working at ground level and lifting a completed element are being applied to a variety of applications:


Wall panels


Sculptured structural forms


Columns

Featured decorative elements


Beams and Trusses

Stepped beams

The Tilt Up process


Ideally, panels are cast on the surface bed of the project or on final concrete hardstand areas around the building. If project conditions dictate the use of sacrificial casting beds, 75mm thick unreinforced beds are prepared and later demolished and carted off site. This is only done as a last resort in order to minimise unnecessary costs.

Panels are set out in accordance with a predetermined casting layout drawing.

Simple perimeter formwork is erected outlining the shape of the panel as well as any openings required. Decorative relief work can then be prepared where necessary. Should space constraints prevail, similar panels can be stack-cast one on top of another.

  

A chemically reactive bondbreaker is then applied to the casting surface to ensure that there is no adhesion between the panels. The bondbreaker is non membrane forming and has no effect on applied finishes to either the walls or the surface bed.

Reinforcing is either tied in place or prefabricated and placed in position depending on the size and complexity of the panel. Lifting inserts are tied in place and the panel is cast and floated.

Panels must cure for between 5 and 9 days before being lifted, depending on the concrete strength used. On larger projects phased lifting allows panels to be lifted periodically once sufficient panels have been prepared. A balance needs to be struck between optimising crane establishment costs and programming requirements.

Panels are then lifted using a mobile crane, placed in their final position and temporarily braced. Braces have an 450mm long adjustable thread, thus allowing the panels to be adjusted and lined at any stage prior to them being finally connected into the structure.

Connections are designed by the project engineer, in consultation with the tilt up supplier to suit the specific requirements of the project. Cast in plates, chemical and expansion anchors, or in-situ concrete stitching are all used, depending on performance requirements.

Once integrated into the final structure the temporary braces are removed and panel joints are sealed internally and externally using a polycord backing and a polyurethane sealant before the final applied finish is added to the panel.

What are the benefits of Tilt Up?

Value
In competitive tender situations, tilt up has repeatedly proven itself to be the most effective method of construction.

The system does not sacrifice quality for cost. Instead, it provides a finished product which is superior to most other alternatives, as it offers the strength and durability of reinforced concrete walls. Simultaneously it is possible to economically achieve aesthetic effects which are either not possible or cost effective with other methods of construction. This ensures attractive, aesthetically pleasing buildings.

 

Programme

Tilt Up is a fast method of construction. Time savings of up to 15% can be achieved over conventional methods due to the following reasons:
  • Fast tracking: - the sequential relationship between activities in conventional construction need not apply to a tilt up alternative. For example, with tilt up it is possible to begin forming and casting wall panels whilst still excavating foundations. This allows overlapping of activities not possible with conventional construction.
  • Increased productivity - by virtue of the fact that with tilt up most of the work is done at ground level, without the need to hoist materials and work at elevated positions, labour is far more productive than is the case conventionally.
  • Reduction in number of trades - since a tilt up panel combines the structures, external envelope and final finish to the building in one operation, there is an obvious reduction in the number of building trades required to achieve the finished product. This reduction in the number of sequential trades automatically results in time savings on the project.
Architectural

The aesthetic possibilites of a tilt up alternative are virtually endless and may be limited only by the architect's imagination. Shapes and designs not possible conventionally can easily be formed and cast to a high degree of accuracy using tilt up.

A tilt up panel is virtually a blank canvas ready to receive any aesthetic the architect requires. Since there are no restrictions due to brick coursing or set module sizes of a cladding system, relief in large panels is not limited to horizontal and vertical bands as tends to be the case conventionally. Instead, a whole range of shapes and effects now become possible. For example, a company logo can easily be incorporated into a tilt up panel simply by forming the logo out of timber or polystyrene and casting the panel over it, thereby recessing the logo within the panel.

Similarly, decorative precast panels can be laid face down and the tilt up panel cast over them, thereby bonding them to the panel, which when lifted, incorporates the decorative panels without any additional fixing requirements.




Flexibility

Tilt up is an extremely flexible system, able to accommodate changes to a building envelope with minimal disruption to the construction programme, or occupants of the building in the case of a completed project.

Openings can be cut into a tilt up panel if required. No lintels are required above new openings as the panel creates a concrete "column and beam" arrangement.

Panels can also be designed to allow for future expansion. Connection details to the main structure are simply detailed allowing the panel to be disconnected from the main structures at a later date. The panel can then be removed and reused in a new position if required.

Reduced maintenance costs and lifecycle benefits

Tilt up buildings are extremely durable and long lasting. There are examples of such buildings that date back to the 1940's, which have recently been given a cosmetic "facelift" and look as good as new.

A tilt up panel is hard and durable. Able to withstand heavy impact loads without any major damage, it is ideal for high wear and tear areas such as warehousing and manufacturing facilities where forklifts are used. Since walls cannot be damaged by forklifts, product can be stored hard up against them, thereby increasing useable space within the structure.

With tilt up one does not have the problem of plaster cracking over time and the high quality finish remains unchanged for decades.

Security

Full height, reinforced concrete walls to the building external envelope provide a virtually impenetrable envelope to even the most determined intruder.

Fire rating

150mm thick tilt up panels have an excellent fire rating over 3 hours. Case studies have shown that even in the event  of a fire, tilt up panels often suffer only cosmetic damage and any remedial work was of a purely decorative nature.

Reduced insurance costs

Due to the fire rating achieved with tilt up, as well as the non-combustible nature of the reinforced concrete walls, a reduction in insurance premiums has often been negotiated by the owners of tilt up buildings.

Conclusion

Clearly one can see that tilt up has evolved to address weaknesses in traditional construction methods, solving problems and challenges faced, whilst delivering a high quality finished product within the tight time and monetary constraints common to modern day projects.

The sytem has only recently started to gain more widespread acceptance within South Africa, but as it continues to meet the demands of our challenging industry, it seems destined to become the construction method of choice.

------------------------------------------


























































 


Tel: +27 11 315 0300 Fax: +27 11 315 0584 E-mail: info@cnci.org.za
About C&CI
Mission & Objectives
C&CI Contacts
Promotion of Access to Information Manual
Map to reach us
Information Centre
Search the C&CI information centres database
Statistics
Concrete Innovations
Concrete Trends
Annual Review
Current Publications
2008 Programme
Ceta Accreditation
General Information
Meeting the demand for skills
Courses 2008
Application Forms
Course Dates
Course Fees
The Cement and Concrete Institute
Maps to Venues
Contact Information
Download Full Education Programme
Ceta Accreditation
New From the School
General Information
Courses 2007
Application Forms
Course Dates
Course Fees
The Cement and Concrete Institute
Maps to Venues
Contact Information
Download Full Education Programme
Qualifications
Unit Standards
Process
NQF Levels
SAQA Database
Reviews and Updates
Search
Feedback, Queries and Comments
Links to other qualifications and units standards
Technical Services
Proficiency Scheme
Consulting Services
Contact Staff
Why Concrete
C&CI's Role
Contacts
Structural Concrete in Action
Education & CPD
Courses & Seminars
Why Concrete
C&CIs Role
Contacts
Concrete Pavements in action
South Africa Focus
Courses & Seminars
cncPave
Civil Construction
Building Projects
Creative Concrete