|
TILT-UP CONSTRUCTION
Tilt Up is
without doubt an improved method of construction that has
evolved to meet the changing needs of our industry and in so
doing, elevates the construction industry by ensuring:
- Quality
- Speed
- Durability
- Cost effectiveness
- Efficient utilisation of available
unskilled and semi-skilled labour resources
So what is
Tilt Up?
- Tilt Up can
be defined as the on-site
casting of large concrete elements that are lifted once by means of a
mobile crane, placed in their final position, and temporarily braced
until being connected into a unified structure.
- Unlike
precast panels that are generally
used as a cladding, a tilt up panel acts as a structural element within
the building capable of carrying roof and slab loads.

- The
technology generally utilises lifting
inserts cast into the face of the elements, thereby drastically
reducing erection stresses by spreading the erection loads evenly over
the element.
- Lifting
inserts are positioned relative
to the centre of gravity of the panel to ensure that the rigging
rotates through snatch blocks as the panel is lifted, until it hangs
slightly out of plumb once lifted off the ground.
- Other than
the final applied finish,
panels require no further finishing as they offer a powerfloated
finish to both external and internal faces.
- A tilt up
panel therefore, provides the
building structure an envelope and final finish in one operation.
What can be
done with tilt up?
Tilt up is an extremely versatile
method
of construction offering a cost effective solution to many challenges
it is presented with. Initially used to create simple wall panels, tilt
up has itself evolved to the point where the benefits of working at
ground level and lifting a completed element are being applied to a
variety of applications:
The Tilt Up
process
Ideally,
panels are cast on the surface
bed of the project or on final concrete hardstand areas around the
building. If project conditions dictate the use of sacrificial casting
beds, 75mm thick unreinforced beds are prepared and later demolished
and carted off site. This is only done as a last resort in order to
minimise unnecessary costs.
Panels are set out in accordance with a predetermined casting layout
drawing.
Simple perimeter formwork is erected outlining the shape of the panel
as well as any openings required. Decorative relief work can then be
prepared where necessary. Should space constraints prevail, similar
panels can be stack-cast one on top of another.
A chemically reactive bondbreaker is then applied to the casting
surface to ensure that there is no adhesion between the panels. The
bondbreaker is non membrane forming and has no effect on applied
finishes to either the walls or the surface bed.
 Reinforcing
is either tied in place or prefabricated and placed in
position depending on the size and complexity of the panel. Lifting
inserts are tied in place and the panel is cast and floated.
Panels must cure for between 5 and 9 days before being lifted,
depending
on the concrete strength used. On larger projects phased lifting allows
panels to be lifted periodically once sufficient panels have been
prepared. A balance needs to be struck between optimising crane
establishment costs and programming requirements.
Panels are then lifted using a mobile crane, placed in their final
position and temporarily braced. Braces have an 450mm long adjustable
thread, thus allowing the panels to be adjusted and lined at any
stage prior to them being finally connected into the structure.
Connections are designed by the project engineer, in consultation with
the tilt up supplier to suit the specific requirements of the project.
Cast in plates, chemical and expansion anchors, or in-situ concrete
stitching are all used, depending on performance requirements.
Once integrated into the final structure the temporary braces are
removed and panel joints are sealed internally and externally using a
polycord backing and a polyurethane sealant before the final applied
finish is added to the panel.
What are the
benefits of Tilt Up?
Value
In
competitive tender situations, tilt up has repeatedly proven itself
to be the most effective method of construction.
The system does not sacrifice quality for cost. Instead, it provides a
finished product which is superior to most other alternatives, as it
offers the strength and durability of reinforced concrete walls.
Simultaneously it is possible to economically achieve aesthetic effects
which are either not possible or cost effective with other methods of
construction. This ensures attractive, aesthetically pleasing
buildings.
Programme
Tilt Up is a
fast method of construction. Time savings of up to 15% can
be achieved over conventional methods due to the following reasons:
- Fast tracking: - the sequential
relationship between
activities in conventional construction need not apply to a tilt up
alternative. For example, with tilt up it is possible to begin forming
and casting wall panels whilst still excavating foundations. This
allows
overlapping of activities not possible with conventional construction.
- Increased productivity - by virtue of the
fact that with tilt up most
of the work is done at ground level, without the need to hoist
materials and work at elevated positions, labour is far more
productive than is the case conventionally.
- Reduction in number of trades - since a
tilt up panel combines the
structures, external envelope and final finish to the building in one
operation, there is an obvious reduction in the number of building
trades required to achieve the finished product. This reduction in the
number of sequential trades automatically results in time savings on
the
project.
Architectural
The
aesthetic possibilites of a tilt up
alternative are virtually endless and may be limited only by the
architect's imagination. Shapes and designs not possible conventionally
can easily be formed and cast to a high degree of accuracy using tilt
up.
A tilt up panel is virtually a blank canvas ready to receive any
aesthetic the architect requires. Since there are no restrictions due
to
brick coursing or set module sizes of a cladding system, relief in
large panels is not limited to horizontal and vertical bands as tends
to be the case conventionally. Instead, a whole range of shapes and
effects now become possible. For example, a company logo can easily be
incorporated into a tilt up panel simply by forming the logo out of
timber or polystyrene and casting the panel over it, thereby recessing
the logo within the panel.
Similarly, decorative precast panels can be laid face down and the tilt
up panel cast over them, thereby bonding them to the panel, which when
lifted, incorporates the decorative panels without any additional
fixing requirements.
Flexibility
Tilt up is an
extremely flexible system, able to accommodate changes to
a building envelope with minimal disruption to the construction
programme, or occupants of the building in the case of a completed
project.
Openings can be cut into a tilt up panel if required. No lintels are
required above new openings as the panel creates a concrete "column and
beam" arrangement.
Panels can also be designed to allow for future expansion. Connection
details to the main structure are simply detailed allowing the panel to
be disconnected from the main structures at a later date. The panel can
then be removed and reused in a new position if required.
Reduced
maintenance costs and lifecycle benefits
Tilt up
buildings are extremely durable and long lasting. There are
examples of such buildings that date back to the 1940's, which have
recently been given a cosmetic "facelift" and look as good as new.
A tilt up panel is hard and durable. Able to withstand heavy impact
loads without any major damage, it is ideal for high wear and tear
areas such as warehousing and manufacturing facilities where forklifts
are used. Since walls cannot be damaged by forklifts, product can be
stored hard up against them, thereby increasing useable space within
the structure.
With tilt up one does not have the problem of plaster cracking over
time and the high quality finish remains unchanged for decades.
Security
Full height,
reinforced concrete walls to the building external
envelope provide a virtually impenetrable envelope to even the most
determined intruder.
Fire rating
150mm thick
tilt up panels have an excellent fire rating over 3 hours.
Case studies have shown that even in the event of a fire, tilt
up panels often suffer only cosmetic damage and any remedial work was
of a purely decorative nature.
Reduced
insurance costs
Due to the
fire rating achieved with tilt up, as well as the
non-combustible nature of the reinforced concrete walls, a reduction in
insurance premiums has often been negotiated by the owners of tilt up
buildings.
Conclusion
Clearly one can see that tilt up has
evolved to address weaknesses in
traditional construction methods, solving problems and challenges
faced, whilst delivering a high quality finished product within the
tight time and monetary constraints common to modern day projects.
The sytem has
only recently started to gain more widespread acceptance
within South Africa, but as it continues to meet the demands of our
challenging industry, it seems destined to become the construction
method of choice.
------------------------------------------
|